Homogenous Reactor Project Quarterly Progress Report For Period Ending January 31, 1955

Description: The reactor equipment cell is expected to be completed by February 15. While filled with water, the tank was inspected for leaks, and the few leaks found will have been repaired by February 15. All orders for construction materials placed prior to this quarter have been received. New requisitions issued during the quarter total $16,000. Work orders were issued, and fabrication of all low-pressure-system components was begun in the ORNL shops. The thermal shield around the reactor vessel was spe… more
Date: April 6, 1955
Creator: McDuffie, H. F. & Kelly, D. C.