Improved Miscible Nitrogen Flood Performance Utilizing Advanced Reservoir Characterization and Horizontal Laterals in a Class I Reservoir - East Binger (Marchand) Unit Quarterly Report

Description: Implementation of the work program of Budget Period 2 of the East Binger Unit (''EBU'') DOE Project continues. Significant advances with the reservoir simulation model have led to changes in the program. One planned horizontal well location, EBU 44-3H, has been eliminated from the program, and another, EBU 45-3H, has been deferred, and may be replaced by a vertical well or completely eliminated at a future date. A new horizontal well location, EBU 63-2H, has been added. EBU 74G-2, the one new i… more
Date: May 30, 2003
Creator: Sinner, Joe