100 Areas, January 29 through February 4, 1946
Description:
The B Pile operated 25 MW below rated power level without interruption during the week. The D Pile was shut down on January 29. During the shutdown 103 tubes were discharged. The shut down lasted for 15 hours. During operation after the shut down power was reduced to meet graphite temperature restrictions. The F Pile was run steadily throughout the week at 25 MW below rated level. Iron content in the process water averaged 0.015, 0.011 and 0.010 ppm at B, D, and F Areas, respectively. Examinati…
more
Date:
February 8, 1946
Creator:
Jordan, W. E.
Item Type:
Refine your search to only
Report