2.0 DEMONSTRATION RESPONSIBILITIES AND COMMUNICATION
This section identifies the organizations involved in this demonstration and describes the
primary responsibilities of each organization. It also describes the methods and frequency of
communication that will be used in coordinating the demonstration activities.
2.1 Demonstration Organization and Participants
This demonstration is being conducted by the DSS Developer or assigned representative with
support by Brookhaven National Laboratory (BNL) and Oak Ridge National Laboratory (ORNL)
under the direction of the U.S. Environmental Protection Agency's (EPA) Office of Research and
Development, National Exposure Research Laboratory, Environmental Sciences Division - Las
Vegas, Nevada (CRD-LV) and the Department of Energy's National Analytical Management
Program, (NAMP) Idaho Falls, Idaho. The CRD-LV's role is to administer the CSCT Demonstration
Program with the assistance of the NAMP. BNL's and ORNL's role is to provide technical and
administrative leadership and support while conducting the demonstration.
Participants in this demonstration are listed in Table 2.1. Detailed information on how to
contact the participants is provided in Appendix A. The specific responsibilities of each
demonstration participant are discussed in Section 2.3.
Based on the three endpoints presented in Section 1.0 of this report, the software products
SitePro and ARCVIEW will demonstrate their capabilities for the Visualization endpoint. The
software products EVS, SamplingFX, GroundwaterFX, and SADA will demonstrate their capabilities
on all three endpoints, Visualization, Sample Optimization, and Cost/Benefit analysis.
2.2 Organization
An organization chart presenting the relationship between the different participants is
displayed in Figure 1. The roles and responsibilities of each participant are discussed in Section 2.3.
2.3 Responsibilities
Representatives from BNL and ORNL (Terry Sullivan and Anthony Armstrong), in
consultation with DSS Developers and the EPA project manager, Eric Koglin, are responsible for the
following elements of this demonstration:
" Designing and preparing all elements of the demonstration plan.
" Developing a Quality Assurance Project Plan (QAPP). The nature of this
demonstration prevents the use of typical quality assurance procedures. Section 8 of
this report will discuss how the principles of Quality Assurance will be applied.6
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Sullivan, Terry & Armstrong, Anthony. Decision support software technology demonstration plan, report, September 1, 1998; Upton, New York. (https://digital.library.unt.edu/ark:/67531/metadc712499/m1/15/: accessed July 16, 2024), University of North Texas Libraries, UNT Digital Library, https://digital.library.unt.edu; crediting UNT Libraries Government Documents Department.