The effects of vent-notch area on bulging and thinning during the clad vent test closure-weld operation

PDF Version Also Available for Download.

Description

The internal gas pressure during clad vent set (CVS) welding is vented through aligned vent notches in each cup. For Galileo, Ulysses, and most of Cassini CVS production, the vent-notch dimensional requirements for both cups were as follows: (1) vent-notch depth, 0.15/0.20 mm; (2) vent-notch width, 0.25/0.35 nun; (3) bottom of vent-notch comers, sharp to full radius; (4) top of vent-notch edge, 0.05 mm maximum break; and (5) maximum variation between vent notch and grit-blasted triangle centerlines, 3{degrees}. During the fuel encapsulation operation (with {sup 238}PuO{sub 2} fuel pellets) at Los Alamos National Laboratory (LANL), excessive bulges or blowouts at … continued below

Physical Description

18 p.

Creation Information

Ulrich, G. B. September 1, 1996.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by the UNT Libraries Government Documents Department to the UNT Digital Library, a digital repository hosted by the UNT Libraries. It has been viewed 226 times. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Author

Sponsor

Publisher

  • Oak Ridge Y-12 Plant
    Publisher Info: Oak Ridge Y-12 Plant, TN (United States)
    Place of Publication: Tennessee

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

The internal gas pressure during clad vent set (CVS) welding is vented through aligned vent notches in each cup. For Galileo, Ulysses, and most of Cassini CVS production, the vent-notch dimensional requirements for both cups were as follows: (1) vent-notch depth, 0.15/0.20 mm; (2) vent-notch width, 0.25/0.35 nun; (3) bottom of vent-notch comers, sharp to full radius; (4) top of vent-notch edge, 0.05 mm maximum break; and (5) maximum variation between vent notch and grit-blasted triangle centerlines, 3{degrees}. During the fuel encapsulation operation (with {sup 238}PuO{sub 2} fuel pellets) at Los Alamos National Laboratory (LANL), excessive bulges or blowouts at the CVS closure-weld tie-in location occurred with 11.8% (27 out of 229) of the flight-quality welds made with the aforementioned standard vent-notch dimensions. These bulges and blowouts are primarily the result of inadequate venting of the increased gas pressure during the thermal cycle of the closure-weld operation. Proper venting is dependent mostly upon the weld parameters and the total vent-notch area. Because of the increased incidence of bulges/blowouts in the {sup 238}PuO{sub 2}-fueled CVS units, LANL personnel requested that consideration be given to increasing the vent-notch size to minimize further the loss of CVS hardware and the potential loss of {sup 238}PuO{sub 2} pellets. Thus, increasing further the production yield of the closure-weld operation would avoid potentially severe schedule delays.

Physical Description

18 p.

Notes

OSTI as DE97002831

Source

  • Other Information: PBD: Sep 1996

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • September 1, 1996

Added to The UNT Digital Library

  • July 25, 2015, 2:20 a.m.

Description Last Updated

  • April 8, 2016, 5:08 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 226

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

International Image Interoperability Framework

IIF Logo

We support the IIIF Presentation API

Ulrich, G. B. The effects of vent-notch area on bulging and thinning during the clad vent test closure-weld operation, report, September 1, 1996; Tennessee. (https://digital.library.unt.edu/ark:/67531/metadc674283/: accessed June 6, 2024), University of North Texas Libraries, UNT Digital Library, https://digital.library.unt.edu; crediting UNT Libraries Government Documents Department.