40-kW field test power plant modification and development. Monthly technical status report No. 13, September 16, 1978-October 15, 1978
Description:
The contract objective is to complete the design and development actions that upgrade the 40-kW fuel cell power plant to a configuration suitable for on-site demonstration testing. The modifications will improve operating capability, durability and maintenance interval and lead to reduced production costs. Equipment to recover and use the by-product heat of electric generation will be available on the power plant for field verification of on-site heat recovery. The 40-kW power plant will be com…
more
Date:
November 10, 1978
Partner: