PAR Loop Schedule Review
Description:
The schedule for the installation of the PAR slurry loop experiment in the South Facility of the ORR has been reviewed and revised. The design, fabrication, and installation is approximately two weeks behind schedule at this time due to many factors; however, indications are that this time can be made up. Design is estimated to be 56 per cent complete, fabrication 27 per cent complete-and installation 11 per cent complete: