15 Matching Results

Search Results

Advanced search parameters have been applied.

Office of Inspector General report on audit of Southwestern Federal Power System combined financial statements and supplemental schedules (with independent auditors` reports thereon) for the years ended September 30, 1997 and 1996

Description: Southwestern Federal Power System (SWFPS) encompasses the operation of 24 hydroelectric power plants by the US Army Corps of Engineers and the marketing of power and energy from those plants by the Southwestern Power Administration (Southwestern) of the US Department of Energy. This report presents the results of the independent certified public accountants` audit of the SWFPS`s combined power system statements of assets, Federal investments and liabilities, and the related combined statements of revenues, expenses and accumulated net revenues, and cash flows.
Date: October 6, 1998
Partner: UNT Libraries Government Documents Department

Southwestern Federal Power System 1995 Financial Statement audit under the Chief Financial Officers Act (WR-FC-96-02)

Description: The Southwestern Federal Power System encompasses the operation of 24 hydroelectric power plants by the U.S. Army Corps of Engineers and the marketing of power and energy from those plants by the Southwestern Power Administration of the U.S. Department of Energy. To integrate the operation of these hydroelectric generating plants and to transmit power from the dams to its customers, Southwestern Power Administration (Southwestern) maintains 2,220 kilometers (1,380 miles) of high-voltage transmission lines, 24 substations, and 46 microwave and VHF radio sites. Southwestern`s headquarters are in Tulsa, Oklahoma; its dispatch center is in Springfield, Missouri; and its maintenance crews are based in Jonesboro, Arkansas, in Gore and Tupelo, Oklahoma, and in Springfield, Missouri. Three offices - Power Marketing and Delivery, Maintenance, and Administration and Rates - are responsible for meeting Southwestern`s mission. Twelve of the 24 generating plants are scheduled directly by Southwestern, and a total of 19 contribute to the interconnected system operations. Generation at the five remaining projects (Denison, Narrows, Sam Rayburn, Whitney, and Willis) is used to serve specific customer loads. At the end of fiscal year 1995, Southwestern marketed power and energy to 10 generation and transmission cooperatives, one distribution cooperative, three military installations, 44 municipal utilities, and three municipal utility joint-action agencies. One of the joint-action agencies has its own allocation of power from Southwestern; the other two serve 33 municipal utilities to whom Southwestern has allocated power. The total number of power allocation customers is 92. Additionally, excess energy is occasionally sold to non-allocation utilities.
Date: February 22, 1996
Partner: UNT Libraries Government Documents Department

The energy behind the power. Southwestern Power Administration 1994 annual report

Description: This is the Southwestern Power Administration 1994 annual report. The topics of the report include a letter to the secretary; an overview including the mission statement, a description of the Southwestern Federal Power System, financial statement, performance measurements, national performance review; year in review, summary of results, financial and statistical data and the Southwestern Power Administration Organization.
Date: December 31, 1994
Partner: UNT Libraries Government Documents Department

Southwestern Power Administration annual site environmental report CY 1997

Description: This report provides a synopsis of Southwestern Power Administration`s (Southwestern`s) effectiveness in managing its operations in an environmentally responsible manner. In CY 1997, the Office of Environmental, Safety, and Health was reorganized and incorporated into the Division of Acquisition and Property. The Division of Acquisition, Property, and Environmental Management maintains responsibility for development, oversight, and implementation of environmental programs. Senior Management at Southwestern has taken actions to increase environmental awareness throughout the organization. During CY 1997, (Southwestern) was not involved in any known programs or activities that had adverse impacts on the environment. The 1997 Environmental Appraisal, a portion of Southwestern`s Self-Assessment and Appraisal Program, indicated approximately 90% compliance with Southwestern`s written environmental programs. Southwestern continued to function throughout CY 1997 in an operations and maintenance posture with minor substation projects.
Date: November 1, 1998
Partner: UNT Libraries Government Documents Department

U.S. hydropower resource assessment for Oregon

Description: The US Department of Energy is developing an estimate of the undeveloped hydropower potential in the United States. The Hydropower Evaluation Software (HES) is a computer model that was developed by the Idaho National Engineering and Environmental Laboratory for this purpose. HES measures the undeveloped hydropower resources available in the US, using uniform criteria for measurement. The software was developed and tested using hydropower information and data provided by the Southwestern Power Administration. It is a menu-driven program that allows the personal computer user to assign environmental attributes to potential hydropower sites, calculate development suitability factors for each site based on the environmental attributes present, and generate reports based on these suitability factors. This report describes the resource assessment results for the State of Oregon.
Date: March 1, 1998
Creator: Conner, A.M. & Francfort, J.E.
Partner: UNT Libraries Government Documents Department

U.S. hydropower resource assessment for Maine

Description: The Department of Energy is developing an estimate of the undeveloped hydro-power potential in the United States. The Hydropower Evaluation Software (HES) is a computer model that was developed by the Idaho National Engineering Laboratory for this purpose. The software measures the undeveloped hydropower resources available in the United States, using uniform criteria for measurement. The software was developed and tested using hydropower information and data provided by the Southwestern Power Administration. It is a menu-driven software program that allows the personal computer user to assign environmental attributes to potential hydropower sites, calculate development suitability factors for each site based on the environmental attributes present, and generate reports based on these suitability factors. This report details the resource assessment results for the State of Maine.
Date: July 1, 1995
Creator: Francfort, J.E. & Rinehart, B.N.
Partner: UNT Libraries Government Documents Department

Southwestern Power Administration site environmental report for calendar year 1995. Annual progress report, January 1, 1995--December 31, 1995

Description: During CY 95, Southwestern was not involved in any programs that had a direct effect on the environment. Involving endangered species, protection of wetlands, or increased electromagnetic radiation. Southwestern continued to function throughout the year in an operations and maintenance posture with minor substation projects. Southwestern received two DOe audits, March 1991 and 1993. Southwestern has worked diligently on the DOE approved action plan and has completed the required effort. The audits provided the secretary, DOE headquarters, and Southwestern an indication of the status of southwestern management`s effectiveness in discharging its duties in an environmentally responsible manner. Senior management at southwestern has taken actions to increase environmental awareness throughout the organization which is evidenced by the creation of the environmental, safety, health, and security office. And the establishment of environmental and safety appointed representatives at various field locations.
Date: September 1, 1996
Partner: UNT Libraries Government Documents Department

US hydropower resource assessment for Washington

Description: The U.S. Department of Energy is developing an estimate of the undeveloped hydropower potential in the United States. The Hydropower Evaluation Software (HES) is a computer model that was developed by the Idaho National Engineering Laboratory for this purpose. HES measures the undeveloped hydropower resources available in the United States, using uniform criteria for measurement. The software was developed and tested using hydropower information and data provided by the Southwestern Power Administration. It is a menu-driven program that allows the personal computer user to assign environmental attributes to potential hydropower sites, calculate development suitability factors for each site based on the environmental attributes present, and generate reports based on these suitability factors. This report describes the resource assessment results for the State of Washington.
Date: July 1, 1997
Creator: Conner, A.M. & Francfort, J.E.
Partner: UNT Libraries Government Documents Department

Final environmental assessment for vegetation control at VHF stations, microwave stations, electrical substations, and pole yards

Description: Southwestern Power Adm. operates very high frequency (VHF) and microwave radio stations, electrical substations, and pole yards for electric power transmission throughout AR, MO, and OK. Vegetation growth at the stations must be suppressed for safety of operation and personnel. Southwestern has been using a combination of mechanical/manual and herbicide control for this purpose; Federally- mandated reductions in staff and budgetary resources require Southwestern to evaluate all potentially efficient methods for vegetation control. Three alternatives were examined: no action, mechanical/manual control, and (proposed) a combination of mechanical/manual and herbicide control. Environmental impacts on air and water quality, wetlands, wildlife, endangered species, archaeological and other resources, farmland, human health, transportation, etc. were evaluated.
Date: October 13, 1995
Partner: UNT Libraries Government Documents Department

Southwestern Power Administration site environmental report: Tulsa, Oklahoma, Williams Center Tower I, January 1, 1995--December 31, 1995

Description: During CY 1995, Southwestern was not involved in any programs that had a direct effect on the environment, involving endangered species, protection of wetlands, or increased electromagnetic radiation. Southwestern continued to function throughout the year in an operations and maintenance posture with minor substation projects. Southwestern received two DOE audits, March 1991 and 1993. Southwestern has worked diligently on the DOE approved action plan and has completed the required report. The audits provided the Secretary, DOE Headquarters, and Southwestern an indication of the status of Southwestern management`s effectiveness in discharging its duties in an environmental responsible manner. Senior management at Southwestern has taken actions to increase environmental awareness throughout the organizations which is evidenced by the creation of the Environmental, Safety, Health, and Security Office, and the establishment of environmental and safety appointed representatives at various field locations.
Date: December 31, 1995
Partner: UNT Libraries Government Documents Department

Southwestern Federal Power System combined financial statements and supplemental schedules (with independent auditors` reports thereon) for the years ended September 30, 1996 and 1995

Description: This report presents the results of the independent certified public accountants` audit of the Southwestern Federal Power System`s (SWFPS) combined power system statement of assets, Federal investment and liabilities, and the related combined statements of revenues, expenses and accumulated net revenues, and cash flows. The 1996 financial statement audit was made under the provisions of the Inspector General Act (5 U.S.C. App.), as amended, the Government Management Reform Act (31 U.S.C. 3515), and Office of Management and Budget implementing guidance. The auditors` work was conducted in accordance with generally accepted government auditing standards. To fulfill audit responsibilities, the Office of Inspector General contracted with the independent public accounting firm of KPMG Peak Marwick LLP (KPMG) to conduct the audit for them, subject to their review. The auditors` report on SWFP`s internal control structure disclosed a reportable condition directed to the Southwestern Power Administration concerning a delay in properly classifying the value of plant assets. The report also included two reportable conditions directed to the Army Corps of Engineers regarding the inconsistent calculation of depreciation expense and the misallocation of multipurpose costs. None of these reportable conditions were considered to be material weaknesses. The auditors` report on SWFP`s compliance with laws and regulations disclosed no new instances of noncompliance by Southwestern.
Date: December 4, 1997
Partner: UNT Libraries Government Documents Department

Environmental Assessment for power marketing policy for Southwestern Power Administration

Description: Southwestern Power Administration (Southwestern) needs to renew expiring power sales contracts with new term (10 year) sales contracts. The existing contracts have been in place for several years and many will expire over the next ten years. Southwestern completed an Environmental Assessment on the existing power allocation in June, 1979 (a copy of the EA is attached), and there are no proposed additions of any major new generation resources, service to discrete major new loads, or major changes in operating parameters, beyond those included in the existing power allocation. Impacts from a no action plan, proposed alternative, and market power for less than 10 years are described.
Date: December 1, 1993
Partner: UNT Libraries Government Documents Department

Financial statistics of major publicly owned electric utilities, 1991

Description: The Financial Statistics of Major Publicly Owned Electric Utilities publication presents summary and detailed financial accounting data on the publicly owned electric utilities. The objective of the publication is to provide Federal and State governments, industry, and the general public with data that can be used for policymaking and decisionmaking purposes relating to publicly owned electric utility issues.
Date: March 31, 1993
Partner: UNT Libraries Government Documents Department