Pilot plant test plan, Task IX: technical support. Industrial Low-Btu Fuel Gas Demonstration-Plant Program

Description: The objective of the AAG pilot plant operation is to provide process data for the gasification and related sections of the demonstration plant. Since the pilot plant will not operate at the actual pressure of the demonstration plant, it is planned to perform tests at two different pressures to obtain a sound basis for pressure scale-up. Other objectives are listed briefly.
Date: January 1, 1978
Partner: UNT Libraries Government Documents Department
open access

Fusion utilization projections in the United States energy economy

Description: The following topics are discussed in some detail in this report: (1) applications of fusion energy, (2) fusion implementation in the US energy system, (3) reactor performance requirements, (4) technology for electric applications, and (5) technology for synthetic fuel/chemical applications. (MOW)
Date: November 1, 1979
Creator: Powell, J.R. & Fillo, J.A.
Partner: UNT Libraries Government Documents Department
open access

Energy Program annual report

Description: The national economy is particularly dependent on efficient electrical generation and transportation. Electrical demand continues to grow and will increasingly rely on coal and nuclear fuels. The nuclear power industry still has not found a solution to the problem of disposing of the waste produced by nuclear reactors. Although coal is in ample supply and the infrastructure is in place for its utilization, environmental problems and improved conversion processes remain technical challenges. In … more
Date: February 1, 1988
Creator: Borg, I.Y. (ed.)
Partner: UNT Libraries Government Documents Department
open access

Industrial Fuel Gas Demonstration Plant Program. Monthly and quarterly progress report, 1 April 1978-30 June 1978 (Deliverable No. 12)

Description: The design of the commercial plant was completed and a cost estimate prepared. Most work remaining on Task I relates to: Demonstration Plant recommendations and includes a configuration study, at DOE's request, to evaluate alternatives for the Demo Plant Configuration to achieve the required reliability. The specific alternatives being considered are: A base U-Gas Plant designed to produce 50 MMM Btu/day 365 days per year (the High Reliability case); a base U-Gas Plant plus product storage… more
Date: July 1, 1978
Partner: UNT Libraries Government Documents Department
open access

Enhanced durability and reactivity for zinc ferrite desulfurization sorbent

Description: AMAX Research Development Center (AMAX R D) has been investigating methods for enhancing the reactivity and durability of the zinc ferrite desulfurization sorbent. Zinc ferrite sorbents are intended for use in desulfurization of hot coal gas in integrated gasification combined cycle (IGCC) or molten carbonate fuel cell (MCFC) applications. For the present program, the reactivity of the sorbent may be defined as its sulfur sorption capacity at the breakthrough point and at saturation in a bench-… more
Date: November 14, 1988
Creator: Jha, Mahesh C. & Berggren, Mark H.
Partner: UNT Libraries Government Documents Department
open access

High-temperature turbine technology program hot-gas path development test. Part II. Testing

Description: This topical report of the US Department of Energy High-Temperature Turbine Technology (DOE-HTTT) Phase II program presents the results of testing full-scale water-cooled first-stage and second-stage turbine nozzles at design temperature and pressure to verify that the designs are adequate for operation in a full-scale turbine environment. Low-cycle fatigue life of the nozzles was demonstrated by subjecting cascade assemblies to several hundred simulated startup/shutdown turbine cycles. This te… more
Date: March 1, 1982
Creator: Horner, M. W.
Partner: UNT Libraries Government Documents Department
open access

Industrial Fuel Gas Demonstration-Plant Program. Pretreatment unit options (Deliverable No. 41)

Description: Three approaches to pretreatment for the Industrial Fuel Gas Demonstration Plant project in the Institute of Gas Technology (IGT) Pilot Plant have been examined. Analyses of these approaches, selection of the best alternative among the three, and detailed design and evaluation of cost and schedule impacts were made. The best approach available to pretreatment demonstration is an integrated pretreater - an ash agglomerating gasifier (AAG) that uses the existing AAG system, a new pretreater press… more
Date: December 1, 1978
Partner: UNT Libraries Government Documents Department
open access

Coal Technology Program. Progress report for November 1977

Description: A block of Pittsburgh seam bituminous coal and a block of Wyodak subbituminous coal were pyrolyzed under reducing gas in support of in situ gasification. Information from previously completed block pyrolysis of bituminous coal under an argon atmosphere show that differences in evolved gas result from differences in heating rates. Compared to block pyrolysis at 0.3 C/sup 0//min, block pyrolysis at 3 C/sup 0//min produces less gas but gas with a higher heating value, yielding a higher overall pyr… more
Date: January 1, 1978
Partner: UNT Libraries Government Documents Department
open access

Catalytic steam gasification of bagasse for the production of methanol

Description: Pacific Northwest Laboratory (PNL) tested the catalytic gasification of bagasse for the production of methanol synthesis gas. The process uses steam, indirect heat, and a catalyst to produce synthesis gas in one step in fluidized bed gasifier. Both laboratory and process development scale (nominal 1 ton/day) gasifiers were used to test two different catalyst systems: (1) supported nickel catalysts and (2) alkali carbonates doped on the bagasse. This paper presents the results of laboratory and … more
Date: December 1, 1983
Creator: Baker, E.G. & Brown, M.D.
Partner: UNT Libraries Government Documents Department
open access

Oxidation/gasification of carbon residue on retorted oil shale. Final report

Description: Studies of the oxidation and gasification of oil shale char were extended to an investigation of the effects of mineral catalysis. Six shales with differing mineral compositions were studied, including samples from the saline zone in the Western Colorado and from the Antrim shales of Michigan. Oxidation kinetics data, corrected for mass transfer effects, were compared for all six samples. A high assay shale from Utah and a sample from the saline zone were found to have the highest oxidation rat… more
Date: January 16, 1984
Creator: Thomson, W. J.
Partner: UNT Libraries Government Documents Department
open access

Feasibility Studies of in-Situ Coal Gasification in the Warrior Coal Field. Quarterly Report

Description: Studies in support of in-situ gasification involved experiments in bench-scale combustors where three parameters were varied independently: initial fuel bed temperature, applied air flow and water vapor influx rate. Methods for measuring the thermal conductivity of solids at high temperatures were evaluated and measurements of the thermal conductivity and thermal diffusivity were made over a temperature range for several samples of coke. (LTN)
Date: January 1, 1980
Creator: Douglas, George W. & McKinley, Marvin D.
Partner: UNT Libraries Government Documents Department
open access

Advancement of flash hydrogasification. Quarterly technical progress report, October-December 1984

Description: The design of test hardware and process development unit (PDU) modifications had been completed previously. Task VII involves the fabrication of test hardware and the modification of an existing 1-ton/h hydroliquefaction PDU at Rockwell's facilities for use as a hydrogasifier test facility. Test hardware fabrication has been completed. Modifications to the PDU were completed in July 1984. The modified facility can accommodate both 10- and 20-ft-long hydrogasifier reactors so that residence time… more
Date: September 1, 1985
Creator: Falk, A. Y.
Partner: UNT Libraries Government Documents Department
open access

Industrial fuel gas demonstration plant program. License agreements for proprietary processes. (Deliverable No. 30)

Description: The proprietary processes included within the Industrial Fuel Gas Demonstration Plant are listed. Draft license agreements covering the use of these processes, with the exception of the Westfield Process (Conoco), have been included at the end of this document. Except for the Claus Process (Amoco) all draft license agreements will be executed directly between MLGW and the licensor. All the draft license agreements provided have been prepared by the licensors after preliminary discussions. Prese… more
Date: unknown
Partner: UNT Libraries Government Documents Department
open access

Development of BEACON technology. Quarterly report, April-June 1982

Description: The BEACON process involves the catalytic deposition of a highly reactive form of carbon from a gas stream which contains carbon monoxide. The carbon-depleted gas is combusted with air to produce power, and the carbon is reacted with steam to produce methane or hydrogen. Experiments were continued this quarter with the objective of improving the carbon deposition efficiency using a Paraho retort off-gas mixture. Analysis has shown that the use of the Paraho off-gas to make hydrogen would be att… more
Date: March 1, 1983
Partner: UNT Libraries Government Documents Department
open access

Industrial Fuel Gas Demonstration Plant Program. Procurement schedule for long-lead items (Deliverable No. 48)

Description: The long-lead items required for the Industrial Fuel Gas Demonstration Plant are given. Utilizing the Construction Plan (Deliverable No. 37), which is based upon 48 months to the completion of Phase II, the delivery requirements for each equipment item were determined. Required delivery dates were ascertained from the erection sequence for IFG Demonstration Plant units and equipment items. Lead times established by FWEC procurement personnel were then applied to arrive at a date when procuremen… more
Date: January 1, 1979
Partner: UNT Libraries Government Documents Department
open access

Low-Btu coal-gasification-process design report for Combustion Engineering/Gulf States Utilities coal-gasification demonstration plant. [Natural gas or No. 2 fuel oil to natural gas or No. 2 fuel oil or low Btu gas]

Description: This report describes a coal gasification demonstration plant that was designed to retrofit an existing steam boiler. The design uses Combustion Engineering's air blown, atmospheric pressure, entrained flow coal gasification process to produce low-Btu gas and steam for Gulf States Utilities Nelson No. 3 boiler which is rated at a nominal 150 MW of electrical power. Following the retrofit, the boiler, originally designed to fire natural gas or No. 2 oil, will be able to achieve full load po… more
Date: June 1, 1982
Creator: Andrus, H E; Rebula, E; Thibeault, P R & Koucky, R W
Partner: UNT Libraries Government Documents Department
open access

Methanation in catalyst-sprayed tube wall reactors: a review

Description: The design and operation of catalyst-sprayed tube wall reactors for methanation are discussed. Reactor tubes were either coated on the inner surface or on the outer surface with a Raney nickel catalyst. A liquid coolant, which was opposite the catalyst-reactant gas-side, removed the heat of methanation. Catalyst performance, reactor operating conditions, spent catalyst analyses, and other results are presented for five PDU tests.
Date: September 1, 1980
Creator: Pennline, H. W.; Schehl, R. R.; Haynes, W. P. & Forney, A. J.
Partner: UNT Libraries Government Documents Department
open access

Cold flow model test plan. Task IX. Technical support. Industrial low-Btu gas demonstration-plant program. (Deliverable No. 43)

Description: A cold-flow model is being built to gather information for appropriately designing the venturi and the bottom section of the gasifier to attain the required ash discharge rate in the demonstration plant. Ancillary tasks will investigate the effect of different feed locations and different means of injecting fines. A model is necessary because the operating conditions of the pilot plant gasifier do not permit the type of testing required to meet the above objectives. The pilot plant gasifier has… more
Date: June 1, 1978
Partner: UNT Libraries Government Documents Department
open access

Industrial Low Btu Fuel Gas Demonstration Plant Program: Phase I. Quarterly and annual report, 19 September 1977-31 December 1977

Description: A major problem which arose during the reporting period was that of the completion of the required environmental analysis in order not to impact Phase II of the program. This problem was addressed and a proposed solution was agreed to. A sole source procurement justification for Energy Impact Associates was prepared and submitted to DOE for approval. This sole source procurement will enable construction start as scheduled (8 months after start of Phase II) whereas a competitive procurement of t… more
Date: January 1, 1978
Partner: UNT Libraries Government Documents Department
open access

Energy and technology review

Description: The state of the laboratory address by LLNL Director Roger Batzel is summarized, and a breakdown of the laboratory funding is given. The Livermore defense-related committment is described, including the design and development of advanced nuclear weapons as well as research in inertial confinement fusion, nonnuclear ordnance, and particle beam technology. LLNL is also applying its scientific and engineering resources to the dual challenge of meeting future energy needs without degrading the qual… more
Date: July 1, 1982
Creator: Stowers, I.F.; Crawford, R.B.; Esser, M.A.; Lien, P.L.; O'Neal, E. & Van Dyke, P. (eds.)
Partner: UNT Libraries Government Documents Department
open access

Development of mild gasification process

Description: Under a previous contract with Morgantown Energy Technology Center (METC), Department of Energy (DOE) Contract No. AC21-84MC21108, UCC Research Corporation (UCCRC) built and tested a 1500 lb/day Mild Gasification Process Development Unit (MGU). The MGU, as tested under the previous contract, is shown in Figure 1. Testing completed under the previous contract showed that good quality hydrocarbon liquids and good quality char can be produced in the MGU. However, the MGU is not optimized. The prim… more
Date: November 1, 1987
Creator: Chu, C.I.C. & Gillespie, B.L.
Partner: UNT Libraries Government Documents Department
open access

Development of mild gasification process

Description: Under a previous contract with Morgantown Energy Technology Center (METC), Department of Energy (DOE) Contract No. AC21-84MC21108, UCC Research Corporation (UCCRC) built and tested a 1500 lb/day Mild Gasification Process Development Unit (MGU). The MGU, as tested under the previous contract, is shown in Figure 1. Testing completed under the previous contract showed that good quality hydrocarbon liquids and good quality char can be produced in the MGU. However, the MGU is not optimized. The prim… more
Date: January 1, 1989
Creator: Chu, C.I.C. & Williams, S.W.
Partner: UNT Libraries Government Documents Department