GT-MHR Commercialization Study Technical Progress and Cost Management Report: May 2003

Description: A271 GT-MHR COMMERCIALZATION STUDY TECHNICAL PROGRESS AND COST MANAGEMENT REPORT FOR THE PERIOD MAY 1 THROUGH MAY 31, 2003. Petten advised GA the start of the HFR-EU2 irradiation is being delayed until late July 2004. HFR-EU1 (pebble fuel) is also delayed until February/March 2004. The reason for the delays was implementation of new financial regulations at Petten that delayed the contracts for capsule fabrication. Review of the MHR-2 Fuel Product Specification was completed. Revision of the sp… more
Date: May 1, 2003
Creator: Shenoy, A. S.
Partner: UNT Libraries Government Documents Department