Underground mining and deep geologic disposal - Two compatible and complementary activities

Description: Active and mature underground mining districts offer conditions favorable to deep geologic disposal because their geology is known in more detail, the feasibility of underground excavations has already been demonstrated, mining leaves distinctive footprints and records that alert subsequent generations to the anthropogenic alterations of the underground environment, and subsequent exploration and production proceeds with great care and accuracy to locate and generally to avoid old mine workings. Compatibility of mining with deep geologic waste disposal has been proven by decades of experience with safe storage and disposal in former mines and in the mined-out areas of still active mining operations. Mineral extraction around an intended repository reduces the incentive for future disturbance. Incidental features of mineral exploration and extraction such as lost circulation zones, allochthonous backfill, and permanent surface markers can deter future intrusion into a repository. Thus exploration and production of mineral resources should be compatible with, and complementary to, deep geologic waste disposal.
Date: December 31, 1995
Creator: Rempe, N.T.
Partner: UNT Libraries Government Documents Department

Radiological surveillance of Remedial Action activities at the processing site, Ambrosia Lake, New Mexico, April 12--16, 1993. Final report

Description: The Uranium Mill Tailings Remedial Action (UMTRA) Project`s Technical Assistance Contractor (TAC) performed a radiological surveillance of the Remedial Action Contractor (RAC), MK-Ferguson and CWM Federal Environmental Services, Inc., at the processing site in Ambrosia Lake, New Mexico. The requirements and attributes examined during the audit were developed from reviewing working-level procedures developed by the RAC. Objective evidence, comments, and observations were verified based on investigating procedures, documentation, records located at the site, personal interviews, and tours of the site. No findings were identified during this audit. Ten site-specific observations, three good practice observations, and five programmatic observations are presented in this report. The overall conclusion from the surveillance is that the radiological aspects of the Ambrosia Lake, New Mexico, remedial action program are performed adequately. The results of the good practice observations indicate that the site health physics (HP) staff is taking the initiative to address and resolve potential issues, and implement suggestions useful to the UMTRA Project. However, potential exists for improving designated storage areas for general items, and the RAC Project Office should consider resolving site-specific and procedural inconsistencies.
Date: April 1, 1993
Partner: UNT Libraries Government Documents Department

Environmental Protection Department`s well inventory: Includes current and past monitoring (through the second quarter of 1990)

Description: This report is an inventory of the wells contained in Environmental Protection Department /Environmental Monitoring Section (EPD/EMS) documents since the startup of the Savannah River Site (SRS) and includes wells monitored by special request and SRS research wells. All wells listed in this inventory are monitoring wells unless otherwise indicated. The purpose of this report is as follows: to provide a historical record of the wells that EPD/EMS has monitored, to provide a document containing a list of wells that are currently in the EPD/EMS Groundwater Monitoring Program, and to provide pertinent information about all wells listed in EPD/EMS documents
Date: November 1, 1990
Creator: Rogers, C.D.
Partner: UNT Libraries Government Documents Department

Environmental and Health Protection well inventory: Includes current and past monitoring (as of April 26, 1989)

Description: This report is an inventory of the wells contained in Environmental and Health Protection (EHP) documents since the startup of the Savannah River Site (SRS) and includes wells monitored by special request and SRS research wells. All wells listed in this inventory are monitoring wells unless otherwise indicated. The purpose of this report is as follows: to provide a historical record of the wells that EHP has monitored, to provide a document containing a list of wells that are currently in the Groundwater Monitoring Program, and to provide pertinent information about all wells listed in EHP documents
Date: October 1, 1989
Creator: Rogers, C.D. & Janssen, J.L.
Partner: UNT Libraries Government Documents Department

A manual for implementing residual radioactive material guidelines

Description: This manual presents information for implementing US Department of Energy (DOE) guidelines for residual radioactive material at sites identified by the Formerly Utilized Sites Remedial Action Program (FUSRAP) and the Surplus Facilities Management Program (SFMP). It describes the analysis and models used to derive site-specific guidelines for allowable residual concentrations of radionuclides in soil and the design and use of the RESRAD computer code for calculating guideline values. It also describes procedures for implementing DOE policy for reducing residual radioactivity to levels that are as low as reasonably achievable. 36 refs., 16 figs, 22 tabs.
Date: June 1, 1989
Creator: Gilbert, T.L.; Yu, C.; Yuan, Y.C.; Zielen, A.J.; Jusko, M.J. & Wallo, A. III
Partner: UNT Libraries Government Documents Department

Executive Summary of State Data Related to Abandoned Centralized and Commercial Drilling-Fluid Disposal Sites in Louisiana, New Mexico, Oklahoma, and Texas

Description: This 2003 Spring Semi-Annual Report contains a summary of the Final Technical Report being prepared for the Soil Remediation Requirements at Commercial and Centralized Drilling-Fluid Disposal (CCDD) Sites project funded by the United States Department of Energy under DOE Award No. DE-AC26-99BC15225. The summary describes (1) the objectives of the investigation, (2) a rationale and methodology of the investigation, (3) sources of data, assessment of data quality, and data availability, (4) examples of well documented centralized and commercial drilling-fluid disposal (CCDD) sites and other sites where drilling fluid was disposed of, and (5) examples of abandoned sites and measures undertaken for their assessment and remediation. The report also includes most of the figures, tables, and appendices that will be included in the final report.
Date: March 1, 2003
Creator: Nance, H. Seay
Partner: UNT Libraries Government Documents Department

THE REMEDIATION OF ABANDONED IRON ORE MINE SUBSIDENCE IN ROCKAWAY TONWSHIP, NEW JERSEY

Description: This report represents the tenth Semi-Annual Technical Progress Report issued in connection with the subsidence remediation projects undertaken by Rockaway Township in Morris County, New Jersey. This report provides a summary of the major project work accomplished during this reporting period and contemplated for the subsequent reporting period. This report is issued as part of the project reporting provisions set forth in the Cooperators Agreement between the United States Government-Department of Energy, and Rockaway Township. The purpose of the Cooperators Agreement is for the Department of Energy to provide technical and financial assistance in a coordinated effort with Rockaway Township to develop and implement a multi-phased plan to remediate ground stability problems associated with abandoned mining activity. Primarily during the 1800's, extensive iron ore mining and prospecting was undertaken in Rockaway Township, part of the Dover District Mining region in Morris County. The abandoned mining activity has resulted in public safety hazards associated with ground collapse and surface subsidence features evolving in both developed and undeveloped areas within Rockaway Township. At the Green Pond Mine site at the Township Compost Storage Facility, engineering continued during this reporting period toward development of the Construction Plans and Technical Specifications for the remediation work. At the Mt. Hope Road subsidence, surface monitoring was conducted periodically at the work area and adjacent areas after the January 2000 construction effort.
Date: February 1, 2003
Creator: Gartenberg, Gary
Partner: UNT Libraries Government Documents Department

Radiological surveillance of Remedial Action activities at the processing site, Falls City, Texas. Final report

Description: The Uranium Mill Tailings Remedial Action (UMTRA) Project`s Technical Assistance Contractor (TAC) performed a radiological surveillance of the Remedial Action Contractor (RAC), MK-Ferguson and CWM Federal Environmental Services, Inc., at the processing site in Falls City, Texas. This surveillance was conducted March 22--26, 1993. No findings were identified during the surveillance. Three site-specific observations and three programmatic observations are presented in this report. The overall conclusion from the surveillance is that the radiological aspects of the Falls City, Texas, remedial action program are performed adequately. However, some of the observations identify that there is potential for improving certain aspects of the occupational radiological air sampling, ensuring analytical data quality, and in communicating with the DOE and TAC on the ore sampling methods. The TAC has also received and is currently reviewing the RAC`s responses regarding the observations identified during the radiological surveillance performed October 29--30, 1992.
Date: April 1, 1993
Partner: UNT Libraries Government Documents Department

Old-field plant succession on the Pajarito Plateau

Description: Eight fallow historic fields of the ponderosa pine and pinon-juniper cover types were surveyed to determine species composition and distribution. The purpose of the study was to understand plant succession on old fields as related to mechanically manipulated sites such as material disposal areas (MDAs). Additionally, the authors wanted a listing of species on disturbed lands of the Pajarito Plateau to aide in the reclamation planning of MDAs using native species. They also wanted to determine if any species could be used as an indicator of disturbance. The eight historic fields were all within Los Alamos County, New Mexico, and had been abandoned in 1943. Two sites were within the boundaries of Los Alamos National Laboratory and were studied both in 1982 and 1993. The study provides a description of each of the field sites, historic information about the homesteads from patent applications, a photographic record of some of the sites, and a listing of species found within each field. The study showed that there were 78 different plant species found on disturbed sites. Of these 78 species, 23 were found to be dominant on one or more of the MDAs or old fields. Although, the disturbance history of each site is imperfectly known, the study does provide an indication of successional processes within disturbed sites of the Pajarito Plateau. Additionally, it provides a listing of species that will invade disturbed sites, species that may be used in site reclamation.
Date: October 1, 1997
Creator: Foxx, T.; Mullen, M.; Salisbury, M. & Tierney, G.
Partner: UNT Libraries Government Documents Department

Uranium Mill Tailings Remedial Action Project (UMTRAP), Slick Rock, Colorado, Revision 1. Bid schedule, special conditions, specifications, and subcontract drawings

Description: This volume contains: bidding requirements; terms and conditions; specifications for Division 1 -- general requirements; specifications for Division 2 -- sitework; specifications for Divisions 5 -- metals; subcontract drawings, (general, Union Carbide processing site, North Continent processing site, and Burro Canyon disposal site).
Date: October 1, 1995
Partner: UNT Libraries Government Documents Department

Results of the independent radiological verification survey at the former C.H. Schnoor and Company Site, 644 Garfield Street, Springdale, Pennsylvania (CPV001)

Description: At the request of the U.S. Department of Energy (DOE), a team from Oak Ridge National Laboratory (ORNL) conducted an independent radiological verification survey at the former C. H. Schnoor and Company Site in Springdale, Pennsylvania. The survey was performed from August to October of 1994. The purpose of the survey was to verify that the site was remediated to levels below DOE guidelines from FUSRAP sites. Results of the independent radiological verification survey at the former C. H. Schnoor and Company Site confirm that the residual uranium contamination at the site is below DOE FUSRAP guidelines for unrestricted use.
Date: September 1, 1995
Creator: Murray, M.E.; Brown, K.S. & Foley, R.D.
Partner: UNT Libraries Government Documents Department

Results of the supplementary radiological survey at the former C. H. Schnoor and Company site, 644 Garfield Street, Springdale, Pennsylvania (CVP001)

Description: At the request of the U.S. Department of Energy (DOE), a team from Oak Ridge National Laboratory conducted radiological surveys at the former C. H. Schnoor and Company site, 644 Garfield Street, Springdale, Pennsylvania. The surveys were performed on October 11-13 and November 14-17, 1993, in order to provide a complete characterization prior to site remediation. The surveys included a gamma scan and a scan for surface contamination from alpha and beta-gamma emitters; measurement of direct and removable alpha and beta-gamma levels; systematic FIDLER measurements at the surface of the concrete; and the collection of samples from boreholes for radionuclide analysis. Results of the surveys revealed radionuclide concentrations and surface contamination levels in excess of applicable DOE guidelines for {sup 238}U. Radionuclide distributions were higher than typical background levels for {sup 238}U in the Springdale, Pennsylvania area.
Date: April 1, 1995
Creator: Coleman, R.L.; Murray, M.E. & Brown, K.S.
Partner: UNT Libraries Government Documents Department

Final audit report of remedial action construction at the UMTRA Project Falls City, Texas, site

Description: This final audit report for the Falls City, Texas, Uranium Mill Tailings Remedial Action Project site summarizes the radiological audits and the quality assurance (QA) in-process surveillances, audits, and final close-out inspection performed by the U.S. Department of Energy (DOE) and Technical Assistance Contractor (TAC). It also summarizes U.S. Nuclear Regulatory Commission (NRC) surveillances. One radiological audit and three radiological surveillances were performed at the Falls City site. These surveillances and audit, which resulted in 31 observations, focused primarily on processing site activities and were performed on the following dates: 3-6 August 1992, 29-30 October 1992, 22-26 March 1993, and 1-3 November 1993. All outstanding radiological issues were closed out at the completion of the construction activities. Six QA in-process surveillances, which resulted in 71 observations, were performed at the Falls City site on the following dates: 22-24 July 1992, 23-25 November 1992, 17-19 May 1993, 16-18 August 1993, 13-15 October 1993, and 2-4 February 1994. All outstanding issues were closed out with the February surveillance on 3 March 1994. The DOE/TAC remedial action close-out inspections of the Falls City site, which resulted in 56 observations, were conducted 9-10 June 1994 and 26 July 1994. The inspections were closed out on 26 January 1995. The NRC performed three on-site construction reviews (OSCR), resulting in seven observations of remedial action construction activities that occurred during site visits. The OSCRs were performed 9 December 1992, 12 May 1993, and 25 October 1993. Since all audit and surveillance observations and recommendations have been closed out, this final audit report segment of the site certification process is complete.
Date: May 1, 1995
Partner: UNT Libraries Government Documents Department

Radiological verification survey results at 14 Peck Ave., Pequannock, New Jersey (PJ001V)

Description: The U.S. Department of Energy (DOE) conducted remedial action during 1993 at the Pompton Plains Railroad Spur and eight vicinity properties in the Wayne and Pequannock Townships in New Jersey as part of the Formerly Utilized Sites Remedial Action Program (FUSRAP). These properties are in the vicinity of the DOE-owned Wayne Interim Storage Site (WISS), formerly the W. R. Grace facility. The property at 14 Peck Ave., Pequannock, New Jersey is one of these vicinity properties. At the request of DOE, a team from Oak Ridge National Laboratory conducted an independent radiological verification survey at this property. The purpose of the survey, conducted between September and December 1993, was to confirm the success of the remedial actions performed to remove any radioactive materials in excess of the identified guidelines. The verification survey included surface gamma scans and gamma readings at 1 meter, beta-gamma scans, and the collection of soil and debris samples for radionuclide analysis. Results of the survey demonstrated that all radiological measurements on the property at 14 Peck Ave. were within applicable DOE guidelines. Based on the results of the remedial action data and confirmed by the verification survey data, the portions of the site that had been remediated during this action successfully meet the DOE remedial action objectives.
Date: May 1995
Creator: Rodriguez, R. E. & Johnson, C. A.
Partner: UNT Libraries Government Documents Department

Nuclear facility decommissioning and site remedial actions

Description: The 576 abstracted references on nuclear facility decommissioning, uranium mill tailings management, and site remedial actions constitute the tenth in a series of reports prepared annually for the US Department of Energy's Remedial Action Programs. Citations to foreign and domestic literature of all types--technical reports, progress reports, journal articles, symposia proceedings, theses, books, patents, legislation, and research project descriptions--have been included. The bibliography contains scientific, technical, economic, regulatory, and legal information pertinent to the US Department of Energy's Remedial Action Programs. Major sections are (1) Surplus Facilities Management Program, (2) Nuclear Facilities Decommissioning, (3) Formerly Utilized Sites Remedial Action Program, (4) Facilities Contaminated with Naturally Occurring Radionuclides, (5) Uranium Mill Tailings Remedial Action Program, (6) Uranium Mill Tailings Management, (7) Technical Measurements Center, and (8) General Remedial Action Program Studies. Within these categories, references are arranged alphabetically by first author. Those references having no individual author are listed by corporate affiliation or by publication description. Indexes are provided for author, corporate affiliation, title work, publication description, geographic location, subject category, and keywords.
Date: September 1, 1989
Creator: Owen, P.T.; Knox, N.P.; Ferguson, S.D.; Fielden, J.M. & Schumann, P.L.
Partner: UNT Libraries Government Documents Department

Preliminary remediation goals for ecological endpoints

Description: Preliminary remediation goals (PRGs) are useful for risk assessment and decision making at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites. PRGs are upper concentration limits for specific chemicals in specific environmental media that are anticipated to protect human health or the environment. They can be used for multiple remedial investigations at multiple facilities. In addition to media and chemicals of potential concern, the development of PRGs generally requires some knowledge or anticipation of future land use. In Preliminary Remediation Goals for Use at the U.S. Department of Energy Oak Ridge Operations Office (Energy Systems 1995), PRGs intended to protect human health were developed with guidance from Risk Assessment Guidance for Superfund: Volume I - Human Health Evaluation Manual, Part B (RAGS) (EPA 1991). However, no guidance was given for PRGs based on ecological risk. The numbers that appear in this volume have, for the most part, been extracted from toxicological benchmarks documents for Oak Ridge National Laboratory (ORNL) and have previously been developed by ORNL. The sources of the quantities, and many of the uncertainties associated with their derivation, are described in this technical memorandum.
Date: July 1, 1996
Creator: Efroymson, R.A.; Suter, G.W. II; Sample, B.E. & Jones, D.S.
Partner: UNT Libraries Government Documents Department

Preliminary characterization of abandoned septic tank systems. Volume 1

Description: This report documents the activities and findings of the Phase I Preliminary Characterization of Abandoned Septic Tank Systems. The purpose of the preliminary characterization activity was to investigate the Tiger Team abandoned septic systems (tanks and associated leachfields) for the purpose of identifying waste streams for closure at a later date. The work performed was not to fully characterize or remediate the sites. The abandoned systems potentially received wastes or effluent from buildings which could have discharged non-domestic, petroleum hydrocarbons, hazardous, radioactive and/or mixed wastes. A total of 20 sites were investigated for the preliminary characterization of identified abandoned septic systems. Of the 20 sites, 19 were located and characterized through samples collected from each tank(s) and, where applicable, associated leachfields. The abandoned septic tank systems are located in Areas 5, 12, 15, 25, and 26 on the Nevada Test Site.
Date: December 1, 1995
Partner: UNT Libraries Government Documents Department

Final report of the decontamination and decommissioning of Building 1 at the Grand Junction Projects Office Facility

Description: The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. Building 1 was found to be radiologically contaminated and was demolished in 1996. The soil beneath and adjacent to the building was remediated in accordance with identified standards and can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.
Date: August 1, 1996
Creator: Widdop, M.R.
Partner: UNT Libraries Government Documents Department

Final report of the decontamination and decommission of Building 31 at the Grand Junction Projects Office Facility

Description: The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the domestic uranium procurement program funded by the U.S. Atomic Energy Commission. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also was the remedial action contractor. Radiological contamination was identified in Building 31 and the building was demolished in 1992. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This area was addressed in the summary final report of the remediation of the exterior areas of the GJPO facility. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.
Date: July 1, 1996
Creator: Krabacher, J.E.
Partner: UNT Libraries Government Documents Department

Remedial action selection report Maybell, Colorado, site. Final report

Description: The Maybell uranium mill tailings site is 25 miles (mi) (40 kilometers [km]) west of the town of Craig, Colorado, in Moffat County, in the northwestern part of the state. The unincorporated town of Maybell is 5 road mi (8 km) southwest of the site. The site is 2.5 mi (4 km) northeast of the Yampa River on relatively flat terrain broken by low, flat-topped mesas. U.S. Highway 40 runs east-west 2 mi (3.2 km) south of the site. The designated site covers approximately 110 acres (ac) (45 hectares [ha]) and consists of a concave-shaped tailings pile and rubble from the demolition of the mill buildings buried in the former mill area. The site is situated between Johnson Wash to the east and Rob Pit Mine to the west. Numerous reclaimed and unreclaimed mines are in the immediate vicinity. Aerial photographs (included at the end of this executive summary) show evidence of mining activity around the Maybell site. Contaminated materials at the Maybell processing site include the tailings pile, which has an average depth of 20 feet (ft) (6 meters [ml]) and contains 2.8 million cubic yards (yd{sup 3}) (2.1 million cubic meters [m{sup 3}]) of tailings. The former mill processing area is on the north side of the site and contains 20,000 yd 3 (15,000 m{sup 3}) of contaminated demolition debris. Off-pile contamination is present and includes areas adjacent to the tailings pile, as well as contamination dispersed by wind and surface water flow. The volume of off-pile contamination to be placed in the disposal cell is 550,000 yd{sup 3}(420,000 m{sup 3}). The total volume of contaminated materials to be disposed of as part of the remedial action is estimated to be 3.37 million yd{sup 3} (2.58 million m{sup 3}).
Date: December 1996
Partner: UNT Libraries Government Documents Department

Contamination source review for Building E3613, Edgewood Area, Aberdeen Proving Ground, Maryland

Description: This report was prepared by Argonne National Laboratory (ANL) to document the results of a contamination source review of Building E3613 at the Aberdeen Proving Ground (APG) in Maryland. The report may be used to assist the U.S. Army in planning for the future use or disposition of this building, The review included a historical records search, physical inspection, photographic documentation, geophysical investigation, and collection of air samples. The field investigations were performed by ANL during 1994 and 1995. Building E3613 (APG designation) is located in the Canal Creek Area of APG. The building was constructed in 1954 for use as a change house, office, and storage building in support of the white phosphorus smoke program. The building has not been used since 1988. During an inspection in 1988, asbestos was listed as the only potential contaminant. The physical inspection and photographic documentation of Building E3613 were completed in November 1994. At the time of the inspection, Building E3613 was inactive and in disrepair. The single-story, rectangular structure contains five rooms and measures 16 ft 2 in. by 32 ft. The building is wood frame construction with a gabled roof. The exterior walls and roof are constructed of wood covered with asphalt sheeting. The building rests on a concrete foundation. The interior walls are 6-in.-thick wood, and the ceiling is assumed to be white drywall nailed to a wooden frame. Overhead steam pipes supported by vertical pipes traverse the area. Two concrete footings for guy wires that support the overhead steam pipes are located north and west of the building. Four additional vertical pipes exit the ground east of the building.
Date: September 1, 1995
Creator: Billmark, K.A.; Emken, M.E. & Muir-Ploense, K.L.
Partner: UNT Libraries Government Documents Department

US Department of Energy Grand Junction Projects Office Remedial Action Project, final report of the decontamination and decommissioning of Building 36 at the Grand Junction Projects Office Facility

Description: The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. Building 36 was found to be radiologically contaminated and was demolished in 1996. The soil beneath the building was remediated in accordance with identified standards and can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.
Date: August 1, 1996
Creator: Widdop, M.R.
Partner: UNT Libraries Government Documents Department

Final report of the decontamination and decommissioning of Building 6 at the Grand Junction Projects Office Facility

Description: The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the domestic uranium procurement program funded by the U.S. Atomic Energy Commission. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, is also the remedial action contractor. Radiological contamination was identified in Building 6, and the building was demolished in 1992. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.
Date: July 1, 1996
Creator: Widdop, M.R.
Partner: UNT Libraries Government Documents Department