Assessment of the Electrical Power Requirements for Continued Safe Storage and Waste Feed Delivery Phase 1

Description: This study evaluated the ability of the electrical distribution system to support safe storage as well as the first phase of the Waste Feed Delivery. Several recommendations are made to improve the electrical system. The ability to assure adequate Waste Feed Delivery (WFD) to the Privatization Contractor's vitrification facility is a key element in the overall Hanford cleanup schedule. An important aspect of this WFD is the availability of sufficient and appropriate electrical power in the single- and double-shell tank farms. The methodology for performing this review and the results are described.
Date: April 7, 2000
Creator: MAY, T.H.
Partner: UNT Libraries Government Documents Department

Baseline Design Compliance Matrix for the Type 4 In Situ Vapor Samplers (ISVS)

Description: The DOE has identified a need to sample vapor space and exhaust ducts in waste tanks that store radioactive waste. This document provides the Design Compliance Matrix (DCM) for the Type 4 In-Situ Vapor Sampling (ISVS) system that is used for completing this sampling function. The DCM identifies the design requirements and the source of the requirements for the Type 4 ISVS system. DCMs are a single-source compilation design requirements for sampling and sampling support equipment and support the configuration management of these systems.
Date: January 25, 2000
Creator: BOGER, R.M.
Partner: UNT Libraries Government Documents Department

River Protection Project (RPP) Environmental Program Plan

Description: This Environmental Program Plan was developed in support of the Integrated Environment, Safety, and Health Management System Plan (ISMS) (RPP-MP-003), which establishes a single, defined environmental, safety, and health management system that integrates requirements into the work planning and execution processes to protect workers, the public, and the environment. The ISMS also provides mechanisms for increasing worker involvement in work planning, including hazard and environmental impact identification, analysis, and control; work execution; and feedback/improvement processes. The ISMS plan consists of six core functions. Each section of this plan describes the activities of the River Protection Project (RPP) (formerly known as the Tank Waste Remediation System) Environmental organization according to the following core functions: Establish Environmental Policy; Define the Scope of Work; Identify Hazards, Environmental Impacts, and Requirements; Analyze Hazards and Environmental Impacts and Implement Controls; Perform Work within Controls; and Provide Feedback and Continuous Improvement.
Date: March 29, 2000
Creator: POWELL, P.A.
Partner: UNT Libraries Government Documents Department

River Protection Project (RPP) Level 0 Logic

Description: The following modifications were made to the River Protection Project Level-0 logic in going from Rev. I to Rev. 2. The first change was the change to the heading at the top of the drawing: ''TWRS Program Logic'' to ''River Protection Project Mission Logic''. Note that purely format changes (e.g., fonts, location of boxes, date format, addition of numbers to ''ghost'' boxes) are not discussed. However, the major format change was to show DOE-BNFL Inc. Interface Control Documents (ICDs) on the logic.
Date: January 20, 2000
Creator: SEEMAN, S.E.
Partner: UNT Libraries Government Documents Department

River Protection Project (RPP) Readiness to Proceed 2 Internal Independent Review Team Final Report

Description: This report describes the results of an independent review team brought in to assess CH2M Hill Hanford Group's readiness and ability to support the RPP's move into its next major phase - retrieval and delivery of tank waste to the Privatization Contractor
Date: March 29, 2000
Creator: SCHAUS, P.S.
Partner: UNT Libraries Government Documents Department

River Protection Project (RPP) Readiness to Proceed 2 Internal Independent Review Team Final Report

Description: This report describes the results of an independent review team brought in to assess CH2M HILL Hanford's readiness and ability to support the RPP's move into its next major phase - retrieval and delivery of tank waste to the Privatization Contractor.
Date: March 15, 2000
Creator: SCHAUS, P.S.
Partner: UNT Libraries Government Documents Department

System Engineering Management and Implementation Plan for Project W-211 Initial Tank Retrieval Systems (ITRS)

Description: This systems Engineering Management and Implementation Plan (SEMIP) describes the Project W-211 implementation of the Tank Farm Contractor Systems Engineering Management Plan (TFC SEMP). The SEMIP defines the systems engineering products and processes used by the project to comply with the TFC SEMP, and provides the basis for tailoring systems engineering processes by applying a graded approach to identify appropriate systems engineering requirements for W-211.
Date: May 5, 2000
Creator: VAN BEEK, J.E.
Partner: UNT Libraries Government Documents Department

Systems Engineering Management Plan for Tank Farm Restoration and Safety Operations Project W-314

Description: The Systems Engineering Management Plan for Project W-314 has been prepared within the guidelines of HNF-SD-WM-SEMP-002, TWRS Systems Engineering Management Plan. The activities within this SEMP have been tailored, in accordance with the TWRS SEMP and DOE Order 430.1, Life Cycle Asset Management, to meet the needs of the project.
Date: April 19, 2000
Creator: MCGREW, D.L.
Partner: UNT Libraries Government Documents Department

Tank 241-AY-101 Privatization Push Mode Core Sampling and Analysis Plan

Description: This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for samples obtained from tank 241-AY-101. The purpose of this sampling event is to obtain information about the characteristics of the contents of 241-AY-101 required to satisfy Data Quality Objectives For RPP Privatization Phase I: Confirm Tank T Is An Appropriate Feed Source For High-Level Waste Feed Batch X(HLW DQO) (Nguyen 1999a), Data Quality Objectives For TWRS Privatization Phase I : Confirm Tank T Is An Appropriate Feed Source For Low-Activity Waste Feed Batch X (LAW DQO) (Nguyen 1999b), Low Activity Waste and High-Level Waste Feed Data Quality Objectives (L and H DQO) (Patello et al. 1999), and Characterization Data Needs for Development, Design, and Operation of Retrieval Equipment Developed through the Data Quality Objective Process (Equipment DQO) (Bloom 1996). Special instructions regarding support to the LAW and HLW DQOs are provided by Baldwin (1999). Push mode core samples will be obtained from risers 15G and 150 to provide sufficient material for the chemical analyses and tests required to satisfy these data quality objectives. The 222-S Laboratory will extrude core samples; composite the liquids and solids; perform chemical analyses on composite and segment samples; archive half-segment samples; and provide subsamples to the Process Chemistry Laboratory. The Process Chemistry Laboratory will prepare test plans and perform process tests to evaluate the behavior of the 241-AY-101 waste undergoing the retrieval and treatment scenarios defined in the applicable DQOs. Requirements for analyses of samples originating in the process tests will be documented in the corresponding test plans and are not within the scope of this SAP.
Date: January 12, 2000
Creator: TEMPLETON, A.M.
Partner: UNT Libraries Government Documents Department

Tank 241-AY-101 Privatization Push Mode Core Sampling and Analysis Plan

Description: This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for samples obtained from tank 241-AY-101. The purpose of this sampling event is to obtain information about the characteristics of the contents of 241-AY-101 required to satisfy ''Data Quality Objectives For RPP Privatization Phase I: Confirm Tank T Is An Appropriate Feed Source For High-Level Waste Feed Batch X(HLW DQO)' (Nguyen 1999a), ''Data Quality Objectives For TWRS Privatization Phase I: Confirm Tank T Is An Appropriate Feed Source For Low-Activity Waste Feed Butch X (LAW DQO) (Nguyen 1999b)'', ''Low Activity Waste and High-Level Waste Feed Data Quality Objectives (L&H DQO)'' (Patello et al. 1999), and ''Characterization Data Needs for Development, Design, and Operation of Retrieval Equipment Developed through the Data Quality Objective Process (Equipment DQO)'' (Bloom 1996). Special instructions regarding support to the LAW and HLW DQOs are provided by Baldwin (1999). Push mode core samples will be obtained from risers 15G and 150 to provide sufficient material for the chemical analyses and tests required to satisfy these data quality objectives. The 222-S Laboratory will extrude core samples; composite the liquids and solids; perform chemical analyses on composite and segment samples; archive half-segment samples; and provide sub-samples to the Process Chemistry Laboratory. The Process Chemistry Laboratory will prepare test plans and perform process tests to evaluate the behavior of the 241-AY-101 waste undergoing the retrieval and treatment scenarios defined in the applicable DQOs. Requirements for analyses of samples originating in the process tests will be documented in the corresponding test plans and are not within the scope of this SAP.
Date: May 19, 2000
Creator: TEMPLETON, A.M.
Partner: UNT Libraries Government Documents Department

Tank 241-AZ-101 Mixer Pump Test Vapor Sampling and Analysis Plan

Description: This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for vapor samples obtained during the operation of mixer pumps in tank 241-AZ-101. The primary purpose of the mixer pump test (MPT) is to demonstrate that the two 300 horsepower mixer pumps installed in tank 241-AZ-101 can mobilize the settled sludge so that it can be retrieved for treatment and vitrification. Sampling will be performed in accordance with Tank 241-AZ-101 Mixer Pump Test Data Quality Objective (Banning 1999) and Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis (Mulkey 1999). The sampling will verify if current air emission estimates used in the permit application are correct and provide information for future air permit applications.
Date: March 6, 2000
Creator: TEMPLETON, A.M.
Partner: UNT Libraries Government Documents Department

Tank 241-AZ-101 Mixer Pump Test Vapor Sampling and Analysis Plan

Description: This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for vapor samples obtained during the operation of mixer pumps in tank 241-AZ-101. The primary purpose of the mixer pump test (MPT) is to demonstrate that the two 300 horsepower mixer pumps installed in tank 241-AZ-101 can mobilize the settled sludge so that it can be retrieved for treatment and vitrification Sampling will be performed in accordance with Tank 241-AZ-101 Mixer Pump Test Data Quality Objective (Banning 1999) and Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis (Mulkey 1999). The sampling will verify if current air emission estimates used in the permit application are correct and provide information for future air permit applications.
Date: January 31, 2000
Creator: TEMPLETON, A.M.
Partner: UNT Libraries Government Documents Department

Tank 241-AZ-101 Mixer Pump Test Vapor Sampling and Analysis Plan

Description: This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for vapor samples obtained during the operation of mixer pumps in tank 241-AZ-101. The primary purpose of the mixer pump test (MPT) is to demonstrate that the two 300 horsepower mixer pumps installed in tank 241-AZ-101 can mobilize the settled sludge so that it can be retrieved for treatment and vitrification. Sampling will be performed in accordance with Tank 241-AZ-101 Mixer Pump Test Data Quality Objective (Banning 1999) and Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis (Mulkey 1999). The sampling will verify if current air emission estimates used in the permit application are correct and provide information for future air permit applications.
Date: April 10, 2000
Creator: TEMPLETON, A.M.
Partner: UNT Libraries Government Documents Department

Process Test Plan Shutdown P16 Exhauster

Description: This Process Test Plan was written to gather temperature data to determine the amount of heat load remaining in tank 241-C-106. This process test plan is being conducted to gather the temperature data necessary to determine how much of the initial heat load is still left in 241-C-106. The heat load will be determined by shutting off the C-106 exhaust system, monitoring the change in tank temperature, and plugging the resulting data into the thermal model for this tank.
Date: January 25, 2000
Creator: PARKMAN, D.B.
Partner: UNT Libraries Government Documents Department

Project Delivery Acquisition and Contracting Plan for the Tank Farm Contractor

Description: This document is a plan presenting the process, strategies and approaches for vendor contracting by the Tank Farm Contractor. The plan focuses on contracting structures, practices, methods, and desired approaches in contracting. The U.S. Department of Energy (DOE), Office of River Protection (ORP) has contracted with the CH2M HILL Hanford Group, Inc. (CHG), as the Tank Farm Contractor (TFC), to support vitrification of Hanford Site tank waste by the Privatization Contractor. During Waste Feed Delivery Phase 1, waste will be retrieved from certain double-shell tanks and delivered to the Privatization Contractor to meet contract feed delivery requirements. Near-term project goals include upgrading infrastructure systems; retrieving and delivering the waste; and accepting the waste packages for interim onsite storage and disposal. Project Delivery includes individual projects assigned to provide the infrastructure and systems responsible to provide engineering, design, procurement, installation/construction, and testing/turnover of systems for retrieval of waste from Hanford double-shell tanks. This plan sets the requirements for projects work scope, contracting practices, structures, methods, and performance measurements. The plan is designed to integrate Life-Cycle Projects acquisitions and provide a consistent contracting approach. This effort will serve as a step improvement in contract reform implementing commercial practices into DOE projects.
Date: April 22, 2000
Creator: Mercado, L. C.
Partner: UNT Libraries Government Documents Department

Project Execution Plan for Project W-211 Initial Tank Retrieval Systems (ITRS)

Description: This Project Execution Plan documents the methodology for managing Project W-211. Project W-211, Initial Tank Retrieval Systems (ITRS), is a fiscal year 1994 Major Systems Acquisition that will provide systems for retrieval of radioactive wastes from selected double-shell tanks (DST). The contents of these tanks are a combination of supernatant liquids and settled solids. To retrieve waste from the tanks, it is first necessary to mix the liquid and solids prior to transferring the slurry to alternative storage or treatment facilities. The ITRS will provide systems to mobilize the settled solids and transfer the wastes out of the tanks. In so doing, ITRS provides feed for the future waste treatment plant, allows for consolidation of tank solids to manage space within existing DST storage capacity, and supports continued safe storage of tank waste. The ITRS scope has been revised to include waste retrieval systems for tanks AP-102, AP-104, AN-102, AN-103, AN-104, AN-105, AY-102, AZ-102, and SY-102. This current tank selection and sequence provides retrieval systems supporting the River Protection Project (RF'P) Waste Treatment Facility and sustains the ability to provide final remediation of several watch list DSTs via treatment. The ITRS is configured to support changing program needs, as constrained by available budget, by maintaining the flexibility for exchanging tanks requiring mixer pump-based retrieval systems and shifting the retrieval sequence. Preliminary design was configured such that an adequate basis exists for initiating Title II design of a mixer pump-based retrieval system for any DST. This Project Execution Plan (PEP), derived from the predecessor Project Management Plan, documents the methodology for managing the ITRS, formalizes organizational responsibilities and interfaces, and identifies project requirements such as change control, design verification, systems engineering, and human factors engineering.
Date: April 19, 2000
Creator: Van Beek, J. E.
Partner: UNT Libraries Government Documents Department

Operational test report integrated system test (ventilation upgrade)

Description: Operational Final Test Report for Integrated Systems, Project W-030 (Phase 2 test, RECIRC and HIGH-HEAT Modes). Project W-030 provides a ventilation upgrade for the four Aging Waste Facility tanks, including upgraded vapor space cooling and filtered venting of tanks AY101, Ay102, AZ101, AZ102.
Date: October 5, 1999
Creator: HARTY, W.M.
Partner: UNT Libraries Government Documents Department

Operational Test Report (OTR) for U-102 Pumping and Instrumentation and Control (PIC) Skid

Description: Attached is the completed Operation Test Procedure (OTP-200-004, Rev. A-19 and Rev. A-20). OTP includes a print out of the Programmable Logic Controller (PLC) Ladder Diagram. Ladder Diagram was designed for installation in the PLC used to monitor and control pumping activity for Tank Farm 241-U-102. The completed OTP and OTR are referenced in the IS PIC Skid Configuration Drawing (H-2-829998).
Date: February 28, 2000
Creator: KOCH, M.R.
Partner: UNT Libraries Government Documents Department

Operational Test Report (OTR) for U-103 Pumping and Instrumentation and Control (PIC) Skid

Description: Attached is the completed Operation Test Procedure (OTP-200-004, Rev. A-16). OTP includes a print out of the Programmable Logic Controller (PLC) Ladder Diagram. Ladder Diagram was designed for installation in the PLC used to monitor and control pumping activity for Tank Farm 241-U-103. The completed OTP and OTR are referenced in the 25 PIC Skid Configuration Drawing (H-2-829998).
Date: February 28, 2000
Creator: KOCH, M.R.
Partner: UNT Libraries Government Documents Department

Operational Test Report (OTR) for U-105 Pumping and Instrumentation and Control (PIC) Skid

Description: Attached is the completed Operation Test Procedure (OTP-200-004, Rev. A-18). OTP includes a print out of the Programmable Logic Controller (PLC) Ladder Diagram. Ladder Diagram was designed for installation in the PLC used to monitor and control pumping activity for Tank Farm 241-U-105. The completed OTP and OTR are referenced in the IS PIC Skid Configuration Drawing (H-2-829998).
Date: February 28, 2000
Creator: KOCH, M.R.
Partner: UNT Libraries Government Documents Department