Homogeneous Reactor Project Quarterly Progress Report: February-April 1960

Description: Report issued by the Oak Ridge National Laboratory discussing quarterly progress made by the Homogeneous Reactor Program. It includes descriptions of progress and studies conducted during the report period, with tables, illustrations, and photographs.
Date: August 9, 1960
Creator: Briggs, R. B.; Beall, S. E.; Lyon, R. N.; Bohlmann, E. G.; Ferguson, D. E.; McDuffie, H. F. et al.
Partner: UNT Libraries Government Documents Department
open access

Homogenous Reactor Project Quarterly Progress Report For Period Ending January 31, 1955

Description: The reactor equipment cell is expected to be completed by February 15. While filled with water, the tank was inspected for leaks, and the few leaks found will have been repaired by February 15. All orders for construction materials placed prior to this quarter have been received. New requisitions issued during the quarter total $16,000. Work orders were issued, and fabrication of all low-pressure-system components was begun in the ORNL shops. The thermal shield around the reactor vessel was spe… more
Date: April 6, 1955
Creator: McDuffie, H. F. & Kelly, D. C.
Partner: UNT Libraries Government Documents Department
open access

Homogenous Reactor Project Quarterly Progress Report For Period Ending April 30, 1955

Description: Part I. Experimental Reactors: The effect of prompt-neutron lifetime upon reactor safety was investigated for the HRT. It was found that for a given pressure rise the allowable rate of reactivity addition was relatively insensitive to the average prompt-neutron lifetime, although the rate de creased somewhat with decreasing lifetime for the higher pressure rises. With only source neutrons present and the reactor initially subcritical, the allowable rate was practically independent of the initia… more
Date: July 14, 1955
Creator: McDuffie, H. F. & Kelly, D. C.
Partner: UNT Libraries Government Documents Department
open access

Homogeneous Reactor Project Progress Report: May-October 1959

Description: Report issued by the Oak Ridge National Laboratory discussing quarterly progress made by the Homogeneous Reactor Program. Descriptions of progress and studies conducted are presented. This report includes tables, illustrations, and photographs.
Date: February 10, 1960
Creator: Briggs, R. B.; Beall, S. E.; Lyon, R. N.; Bohlmann, E. G.; Ferguson, D. E.; McDuffie, H. F. et al.
Partner: UNT Libraries Government Documents Department
open access

Homogeneous Reactor Project Quarterly Progress Report: November 1959-January 1960

Description: From Summary: "The major objective of the run was the investigation of fuel stability. The reactor operated for long periods at the design power of 5 Mw with none of the usual indications of instability while the system pressure was kept at 1250 psig. Run 21 ended on January 22, so that the reason for an abrupt change in the mixing rate of fuel between the core and blanket could be investigated and a reactor steam-system valve could be repaired."
Date: April 29, 1960
Creator: Briggs, R. B.
Partner: UNT Libraries Government Documents Department
open access

Homogeneous Reactor Project Quarterly Progress Report: For Period Ending October 31, 1954

Description: Part I. Experimental Reactors: The design has been completed for all the major high-pressure and low-pressure components except the reactor pressure vessel. Contained in this report are the most recent revisions of the low-pressure-system flow sheet, a description of important details of the reactor cell, and the final design of the main heat exchangers, the inner dump tanks and separator. the recombiner and recombiner-condenser, and the outer dump tank and reflux condenser. Part II. Thorium Br… more
Date: November 1954
Creator: McDuffie, H. F. & Kelly, D. C.
Partner: UNT Libraries Government Documents Department
open access

Homogeneous Reactor Project Quarterly Progress Report for Period Ending July 31, 1955

Description: Construction of the HRT reactor shield tank was completed, and the inside surfaces were painted. The roof structure for the tank is being assembled in preparation for an acceptance pressure test. Service piping and instrument lines are being installed in the central room area by ORNL craft forces. This work is approximately 50% complete. Fabrication of all temperature system components, except the blanket outer storage tanks, has been completed.
Date: October 10, 1955
Creator: McDuffie, H. F. & Kelly, D. C.
Partner: UNT Libraries Government Documents Department
open access

The Case for the "Steady State" Homogeneous Reactor

Description: The advantages and disadvantages of internal and external O2 and H2 recombination in homogeneous reactors are reviewed. The use of copper as a catalyst for internal recombination is strongly recommended.
Date: December 26, 1952
Creator: Secoy, C. H. & McDuffie, H. F.
Partner: UNT Libraries Government Documents Department