Homogenous Reactor Project Quarterly Progress Report For Period Ending January 31, 1955

Description: The reactor equipment cell is expected to be completed by February 15. While filled with water, the tank was inspected for leaks, and the few leaks found will have been repaired by February 15. All orders for construction materials placed prior to this quarter have been received. New requisitions issued during the quarter total $16,000. Work orders were issued, and fabrication of all low-pressure-system components was begun in the ORNL shops. The thermal shield around the reactor vessel was spe… more
Date: April 6, 1955
Creator: McDuffie, H. F. & Kelly, D. C.
Partner: UNT Libraries Government Documents Department
open access

Homogenous Reactor Project Quarterly Progress Report For Period Ending April 30, 1955

Description: Part I. Experimental Reactors: The effect of prompt-neutron lifetime upon reactor safety was investigated for the HRT. It was found that for a given pressure rise the allowable rate of reactivity addition was relatively insensitive to the average prompt-neutron lifetime, although the rate de creased somewhat with decreasing lifetime for the higher pressure rises. With only source neutrons present and the reactor initially subcritical, the allowable rate was practically independent of the initia… more
Date: July 14, 1955
Creator: McDuffie, H. F. & Kelly, D. C.
Partner: UNT Libraries Government Documents Department
open access

Homogeneous Reactor Project Quarterly Progress Report: For Period Ending October 31, 1954

Description: Part I. Experimental Reactors: The design has been completed for all the major high-pressure and low-pressure components except the reactor pressure vessel. Contained in this report are the most recent revisions of the low-pressure-system flow sheet, a description of important details of the reactor cell, and the final design of the main heat exchangers, the inner dump tanks and separator. the recombiner and recombiner-condenser, and the outer dump tank and reflux condenser. Part II. Thorium Br… more
Date: November 1954
Creator: McDuffie, H. F. & Kelly, D. C.
Partner: UNT Libraries Government Documents Department
open access

Homogeneous Reactor Project Quarterly Progress Report for Period Ending July 31, 1955

Description: Construction of the HRT reactor shield tank was completed, and the inside surfaces were painted. The roof structure for the tank is being assembled in preparation for an acceptance pressure test. Service piping and instrument lines are being installed in the central room area by ORNL craft forces. This work is approximately 50% complete. Fabrication of all temperature system components, except the blanket outer storage tanks, has been completed.
Date: October 10, 1955
Creator: McDuffie, H. F. & Kelly, D. C.
Partner: UNT Libraries Government Documents Department
open access

Homogeneous Reactor Project Quarterly Progress Report for Period Ending July 31, 1955

Description: 8 5 6 2 0 5 8 5 5 ? 5 : tion of the HRT is summarized. The design of some reactor components is described, including fuel system line coolers, the thermal shield, instrument cubicles, the reactor cell air monitor, and sampling facilities. The important design specifications for the HRT fissionproduct adsorption system are outlined. The effects of fluid circulation on HRT stability, the results of the rupture of the fuel inlet nozzle on the pressure vessel, core tank temperature, and heat genera… more
Date: August 1, 1955
Creator: McDuffle, H. F. & Kelly, D. C.
Partner: UNT Libraries Government Documents Department