Railplug Ignition System for Enhanced Engine Performance and Reduced Maintenance Progress Report

Description: During the first 6 months of this project, four subtasks were scheduled. Two of these commenced earlier than originally proposed. The experimental task, development of new railplug designs, was completed on schedule. The three numerical subtasks were not completed on schedule. However, this is not expected to affect the capability to complete the overall project on schedule. Because we are early in the project, no results or conclusions were generated. Our progress included development of new r… more
Date: May 29, 2003
Creator: Matthews, Ron
Partner: UNT Libraries Government Documents Department