SNAP Programs Quarterly Progress Report, Task 8--Stontium-90 Fuled Thermoelectric Generator Development: Number 7, May 1, 1962-July 31, 1962
Description:
From introduction and summary: The effort in this area (Task 8 portion of contract) has been confined to operating the reliability model. There have been fluctuations in output power that can be attributed to variations in the operating parameters, plus an increase in the internal resistance.
Date:
1962
Creator:
McDonald, W. A.
Item Type:
Refine your search to only
Report