E.I. du Pont de Nemours & Company Heavy Water Technology Section Monthly Progress Report: October 1956

Description: Monthly report documenting that average daily production was 4.4% higher in October than in September and a new record was established, rotating equipment performance was average with failures of one pump packing and three blower seals, and Units 32 and 33 withstood annual hydrotest without major failure.
Date: November 14, 1956
open access

E.I. du Pont de Nemours & Company Heavy Water Technology Section Monthly Progress Report: September 1956

Description: Monthly report documenting that average daily heavy water production was 6% higher in September than August, 7 shutdowns and 20 mechanical failures occurred in September as compared to 21 and 27, respectively, during August, and rotating equipment performance was below average with failures of one pump packing.
Date: October 15, 1956