Baseline Risk Assessment of Ground Water Contamination at the Uranium Mill Tailings Site Near Green River, Utah

Description: This document evaluates potential impacts to public health and the environment resulting from ground water contamination at the former uranium mill processing site. The tailings and other contaminated material at this site were placed in a disposal cell on the site in 1989 by the US DOE`s Uranium Mill Tailings Remedial Action (UMTRA) Project. Currently, UMTRA Project is evaluating ground water contamination in this risk assessment.
Date: September 1994
open access

Baseline Risk Assessment of Ground Water Contamination at the Uranium Mill Tailings Site Salt Lake City, Utah

Description: This baseline risk assessment of groundwater contamination at the uranium mill tailings site near Salt Lake City, Utah, evaluates potential public health or environmental impacts resulting from ground water contamination at the former uranium ore processing site. The tailings and other contaminated material at this site were placed in a disposal cell located at Clive, Utah, in 1987 by the US Department of Energy`s Uranium Mill Tailings Remedial Action (UMTRA) Project. The second phase of the UM… more
Date: September 1994
open access

Correlation of the West Canyon, Lake Point, and Bannock Peak Limestones (Upper Mississippian to Middle Pennsylvanian), Basal Formations of the Oquirrh Group, Northern Utah and Southeastern Idaho

Description: The following report presents detailed lethologic and conodont biostratigraphic data from four measured sections in the lower part of the Oquirrh Group in the Oquirrh Mountains of Utah and the Deep Creek and Samaria Mountains of Idaho.
Date: 1994
Creator: Davis, L. E.; Dyman, T. S. & Webster, G. D.
open access

[Evolution of Sedimentary Basins--Paradox Basin: Chapters C and D]

Description: From abstract: The report for document C is about the tectonic trends of the northern part of the Paradox Basin of southeastern Utah and southwestern Colorado, as derived from Landsat multispectral scanner imaging and geophysical and geologic mapping. The report for document D is about an uncontrolled X-band airborn radar-image mosaic that was compiled for the western three-fifths of the Moab 1° x 2° quadrangle of southeastern Utah and southwestern Colorado.
Date: 1994
Creator: Friedman, Jules D.; Case, James E.; Simpson, Shirley L. & Heller, Joan S.
open access

Proposed Ground Water Protection Strategy for the Uranium Mill Tailings Site at Green River, Utah. Final Report

Description: This document presents the US DOE water resources protection strategy for the Green River, Utah mill tailings disposal site. The modifications in the original plan are based on new information, including ground water quality data collected after remedial action was completed, and on a revised assessment of disposal cell design features, surface conditions, and site hydrogeology. All aspects are discussed in this report.
Date: November 1994
open access

UMTRA Project Site Observational Work Plan, Mexican Hat, Utah

Description: Surface cleanup activities at the Mexican Hat UMTRA processing site are nearing completion. Ground Water contamination at the Mexican Hat site is a result of uranium milling operations. The extent of residual process water has been identified, and it is limited to the uppermost aquifer in the vicinity of the site. Deeper aquifers are not affected because of an upward hydraulic gradient and the presence of a confining unit (the deeper aquifers are protected by hydrogeologic isolation). The upper… more
Date: September 1994
open access

UMTRA Project Water Sampling and Analysis Plan, Mexican Hat, Utah

Description: The Mexican Hat, Utah, Uranium Mill Tailings Remedial Action (UMTRA) Project site is a former uranium mill that is undergoing surface remediation in the form of on-site tailings stabilization. Contaminated surface materials from the Monument Valley, Arizona, UMTRA Project site have been transported to the Mexican Hat site and are being consolidated with the Mexican Hat tailings. The scheduled completion of the tailings disposal cell is August 1995. Water is found in two geologic units at the si… more