Analysis of diagnostic testing of Gladys McCall Well No. 1

PDF Version Also Available for Download.

Description

Gladys McCall Well No. 1 was flow tested from 1983 to 1987, underwent long-term pressure buildup testing from October 1987 to October 1991, and has recently been re-entered for final diagnostic testing. The combination of a very large, poorly defined reservoir with data from only a single well has required that the testing be carried out over an unusually long time period for an understanding of the pressure maintenance mechanisms to be developed. Ongoing diagnostic testing of the well has been undertaken by DOE to help resolve questions that arose during the analysis of the test data from the eight ... continued below

Creation Information

Riney, T.D. & Garg, S.K. December 1, 1991.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

Gladys McCall Well No. 1 was flow tested from 1983 to 1987, underwent long-term pressure buildup testing from October 1987 to October 1991, and has recently been re-entered for final diagnostic testing. The combination of a very large, poorly defined reservoir with data from only a single well has required that the testing be carried out over an unusually long time period for an understanding of the pressure maintenance mechanisms to be developed. Ongoing diagnostic testing of the well has been undertaken by DOE to help resolve questions that arose during the analysis of the test data from the eight year depletion and recovery testing. A rather complete summary of the synthesis, correlation and analysis of the earlier test data has recently been published (Riney, 1991.) and is included in this report as an Appendix. Figure 1 (an update of Figure 9 in the Appendix) includes the final pressure buildup data in the comparison with the earlier reservoir simulation model. During October 1991 the Gladys McCall well was flowed twice as part of the diagnostic testing. On October 1 flow was started to clean out the well and to perform a spinner survey to determine the fluid entry distribution across the perforated interval of Sand 8. The spinner log was run on October 2 with the well producing at a constant rate of {approx} 4800 stb/d. Total production during the October 1-2 test period was 5954 stb. The second flow was from October 10 to 14 to obtain downhole pressure transient data to determine if the transmissivity (kh product) of Sand 8 had changed during the four-year shutin period (October 1987 to October 1991). The total production during the four day constant-rate (5958 stb/d) drawdown test of October 10-14 was 23,850 stb. Eaton Operating Co. and Institute of Gas Technology are continuing with the diagnostic testing; entry and pressure measurements in two overlaying sands (2 and 4) are planned. Since neither time nor funds are sufficient to complete the Gladys McCall analysis under S-Cubed's FY 1991 Subcontract, this is a preliminary report. It is anticipated that the work will continue under a new FY1992 Subcontract to LBL.

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Report No.: SSS-TR-91-12978
  • Grant Number: DE-AC03-76SF00098
  • DOI: 10.2172/896390 | External Link
  • Office of Scientific & Technical Information Report Number: 896390
  • Archival Resource Key: ark:/67531/metadc879963

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • December 1, 1991

Added to The UNT Digital Library

  • Sept. 22, 2016, 2:13 a.m.

Description Last Updated

  • Nov. 22, 2016, 6:14 p.m.

Usage Statistics

When was this report last used?

Congratulations! It looks like you are the first person to view this item online.

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Riney, T.D. & Garg, S.K. Analysis of diagnostic testing of Gladys McCall Well No. 1, report, December 1, 1991; United States. (digital.library.unt.edu/ark:/67531/metadc879963/: accessed November 22, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.