Decontamination and decommissioning of the EBR-I Complex. Final report

PDF Version Also Available for Download.

Description

This final report covers the Decontamination and Decommissioning (D and D) of the Experimental Breeder Reactor No. 1 (EBR-I) Complex funded under Contract No. AT(10-1)-1375. The major effort consisted of removal and processing of 5500 gallons of sodium/potassium (NaK) coolant from the EBR-I reactor system. Tests were performed to assess the explosive hazards of NaK and KO$sub 2$ in various environments and in contact with various contaminants likely to be encountered in the removal and processing operations. A NaK process plant was designed and constructed and the operation was successfully completed. Lesser effort was required for D and D of … continued below

Creation Information

Kendall, E.W. & Wang, D.K. July 1, 1975.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by the UNT Libraries Government Documents Department to the UNT Digital Library, a digital repository hosted by the UNT Libraries. It has been viewed 384 times. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

This final report covers the Decontamination and Decommissioning (D and D) of the Experimental Breeder Reactor No. 1 (EBR-I) Complex funded under Contract No. AT(10-1)-1375. The major effort consisted of removal and processing of 5500 gallons of sodium/potassium (NaK) coolant from the EBR-I reactor system. Tests were performed to assess the explosive hazards of NaK and KO$sub 2$ in various environments and in contact with various contaminants likely to be encountered in the removal and processing operations. A NaK process plant was designed and constructed and the operation was successfully completed. Lesser effort was required for D and D of the Zero Power Reactor (ZPR-III) Facility, the Argonne Fast Source Reactor (AFSR) Shielding, and removal of contaminated NaK from the storage pit. The D and D effort was completed by 13 June 1975, ahead of schedule. (auth)

Notes

Dep. NTIS

Source

  • Other Information: Orig. Receipt Date: 30-JUN-76

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • July 1, 1975

Added to The UNT Digital Library

  • Sept. 16, 2016, 12:32 a.m.

Usage Statistics

When was this report last used?

Yesterday: 1
Past 30 days: 1
Total Uses: 384

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

International Image Interoperability Framework

IIF Logo

We support the IIIF Presentation API

Kendall, E.W. & Wang, D.K. Decontamination and decommissioning of the EBR-I Complex. Final report, report, July 1, 1975; United States. (https://digital.library.unt.edu/ark:/67531/metadc864484/: accessed April 17, 2024), University of North Texas Libraries, UNT Digital Library, https://digital.library.unt.edu; crediting UNT Libraries Government Documents Department.

Back to Top of Screen