The purpose of this analysis is to provide an engineering excavation and ground support design for the Busted Butte phase II mine back. The analysis will apply engineering practices and previous proven design methods for pillar design and ground support in accordance with applicable Integrated Safety Management principles and functions. The scope of this analysis is limited to the Busted Butte Test Facility. The intended use of this analysis is to provide testing excavation boundaries, ground support and pillar design input to drawing(s) to support test operations implementation. This design activity has been prepared under ''Technical Work Plan For Test ... continued below

Creation Information

Keifer, J.W. November 29, 2000.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Author

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

The purpose of this analysis is to provide an engineering excavation and ground support design for the Busted Butte phase II mine back. The analysis will apply engineering practices and previous proven design methods for pillar design and ground support in accordance with applicable Integrated Safety Management principles and functions. The scope of this analysis is limited to the Busted Butte Test Facility. The intended use of this analysis is to provide testing excavation boundaries, ground support and pillar design input to drawing(s) to support test operations implementation. This design activity has been prepared under ''Technical Work Plan For Test Facilities Design FY01 Work Activities'' (TWP) (CRWMS M&O 2000b). No deviations from the TWP have been necessary for this analysis.

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Report No.: BABEE0000-01717-0200-00025 REV 00
  • Grant Number: NA
  • DOI: 10.2172/850413 | External Link
  • Office of Scientific & Technical Information Report Number: 850413
  • Archival Resource Key: ark:/67531/metadc786418

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • November 29, 2000

Added to The UNT Digital Library

  • Dec. 3, 2015, 9:30 a.m.

Description Last Updated

  • Feb. 10, 2016, 2:57 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 2

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Keifer, J.W. Busted Butte Phase II Excavation Analysis, report, November 29, 2000; Las Vegas, Nevada. (digital.library.unt.edu/ark:/67531/metadc786418/: accessed August 18, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.