DOWNHOLE VIBRATION MONITORING AND CONTROL SYSTEM

PDF Version Also Available for Download.

Description

The project continues to advance approximately per the revised (14-month) schedule. Tasks 1-3 (Modeling, Specification and Design) are all essentially complete. Work has begun on designing the test equipment for the Test and Evaluation (Tasks 4 & 5.) One of the intents of this project is to not only dampen vibration above the damper, but to also dampen vibrations below the damper. This is accomplished by smoothing out the discontinuities as the bit drills ahead. The model has the capability to simulate the drilling looking at the depth of cut along the discontinuities. It can also look at the amount ... continued below

Physical Description

19 pages

Creation Information

Cobern, Martin E. April 1, 2003.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. It has been viewed 18 times . More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

The project continues to advance approximately per the revised (14-month) schedule. Tasks 1-3 (Modeling, Specification and Design) are all essentially complete. Work has begun on designing the test equipment for the Test and Evaluation (Tasks 4 & 5.) One of the intents of this project is to not only dampen vibration above the damper, but to also dampen vibrations below the damper. This is accomplished by smoothing out the discontinuities as the bit drills ahead. The model has the capability to simulate the drilling looking at the depth of cut along the discontinuities. It can also look at the amount of time that the bit is in contact with the formation. It is found that under some conditions the vibrations increased the discontinuities due to resonant conditions. In the ideal situation, the damper reduces the discontinuities and smooths out the drilling. APS looked at a wide range of spring stiffness and damping properties to determine the optimum damper. Spring rates of 10,000 lb/in to 60,000 lbs/in were analyzed. The best compromise is at 30,000 lb/in for the 6 3/4 inch tool. Low spring rates would require large displacements for the damper, while stiff springs do not provide enough motion for the damper. Several damping concepts were analyzed: (1) The first thought was to have a damper providing high damping in the upward direction and low damping in the downward direction. It was found that this increased the vibration by wallowing out the troughs of the discontinuities leading to increased displacements at the bit. (2) Another method investigated was having increased damping at high acceleration levels and less damping at lower acceleration levels. This gave improved results. (3) Constant damping so far provides the damping situation. With the proper damping level the damper can smooth out the discontinuities and provide smooth drilling. However, the damping values are different for different drilling conditions. Different WOB and ROP require different damping coefficients and therefore must be constantly adjusted to provide optimum drilling conditions. The DVMCS system is designed to provide this adjustment (4) Other methods are still being investigated. One method is a constant force damper that might provide optimum damping over a wider range.

Physical Description

19 pages

Notes

OSTI as DE00821466

Source

  • Other Information: PBD: 1 Apr 2003

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Report No.: NONE
  • Grant Number: FC26-02NT41664
  • DOI: 10.2172/821466 | External Link
  • Office of Scientific & Technical Information Report Number: 821466
  • Archival Resource Key: ark:/67531/metadc781588

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • April 1, 2003

Added to The UNT Digital Library

  • Dec. 3, 2015, 9:30 a.m.

Description Last Updated

  • Jan. 3, 2017, 12:20 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 3
Total Uses: 18

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

International Image Interoperability Framework

IIF Logo

We support the IIIF Presentation API

Cobern, Martin E. DOWNHOLE VIBRATION MONITORING AND CONTROL SYSTEM, report, April 1, 2003; United States. (digital.library.unt.edu/ark:/67531/metadc781588/: accessed November 17, 2018), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.