Transport construction status and commissioning plans

PDF Version Also Available for Download.

Description

Installation of the PEP-II electron and positron Injection beamlines in the SLAC linac housing is now underway. Utilization of the existing high power, low emittance beams available at SLAC required that a great portion of the systems for pulsed extraction and transport of 9.0 GeV electrons and 3.1 GeV positrons for injection into the PEP-II rings will reside in the existing linac housing. Approximately 4.7 kilometers of these beamlines will be completed during the summer of 1995. All components, including orbit correctors and diagnostic instruments, required for extraction and transport of the electron beam will be in place and ready ... continued below

Physical Description

3 p.

Creation Information

Fieguth, T.; Bloom, E. & Donaldson, T. June 1, 1995.

Context

This article is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this article can be viewed below.

Who

People and organizations associated with either the creation of this article or its content.

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this article. Follow the links below to find similar items on the Digital Library.

Description

Installation of the PEP-II electron and positron Injection beamlines in the SLAC linac housing is now underway. Utilization of the existing high power, low emittance beams available at SLAC required that a great portion of the systems for pulsed extraction and transport of 9.0 GeV electrons and 3.1 GeV positrons for injection into the PEP-II rings will reside in the existing linac housing. Approximately 4.7 kilometers of these beamlines will be completed during the summer of 1995. All components, including orbit correctors and diagnostic instruments, required for extraction and transport of the electron beam will be in place and ready for commissioning as soon as this fall. The positron transport line in the housing will also be complete except for the pulsed extraction system. These systems are described, along with the status of the construction and installation of the important subsystems such as magnets and power supplies, vacuum systems, instrumentation and controls. The plan for commissioning is discussed.

Physical Description

3 p.

Notes

INIS; OSTI as DE95014650

Source

  • 16. Institute of Electrical and Electronic Engineers (IEEE) particle accelerator conference, Dallas, TX (United States), 1-5 May 1995

Language

Item Type

Identifier

Unique identifying numbers for this article in the Digital Library or other systems.

  • Other: DE95014650
  • Report No.: SLAC-PUB--95-6812
  • Report No.: CONF-950512--188;LBL--37045
  • Grant Number: AC03-76SF00515;AC03-76SF00098
  • Office of Scientific & Technical Information Report Number: 82532
  • Archival Resource Key: ark:/67531/metadc780643

Collections

This article is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this article?

When

Dates and time periods associated with this article.

Creation Date

  • June 1, 1995

Added to The UNT Digital Library

  • Dec. 3, 2015, 9:30 a.m.

Description Last Updated

  • Feb. 2, 2016, 6:12 p.m.

Usage Statistics

When was this article last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 2

Interact With This Article

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Fieguth, T.; Bloom, E. & Donaldson, T. Transport construction status and commissioning plans, article, June 1, 1995; Menlo Park, California. (digital.library.unt.edu/ark:/67531/metadc780643/: accessed December 17, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.