The Waste Isolation Pilot Plant (WIPP) Recertification Project was established to meet the requirement of the WIPP Land Withdrawal Act (LWA)1 to demonstrate continued compliance with U.S. Environmental Protection Agency (EPA) disposal regulations at five-year intervals. This paper delineates the objective of the first recertification effort, sets out project goals, and establishes guiding assumptions. It describes the overall direction for a highly complex and interdependent set of tasks leading to recertification of the WIPP repository in 2004. This paper also lays out a high-level schedule for producing the WIPP Compliance Recertification Application (CRA). The major principle behind recertification is that ... continued below

Physical Description

12 pages

Creation Information

Casey, S. C.; Shoemaker, P. E. & Patterson, R. L. February 25, 2002.

Context

This article is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. It has been viewed 11 times . More information about this article can be viewed below.

Who

People and organizations associated with either the creation of this article or its content.

Sponsor

Publishers

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this article. Follow the links below to find similar items on the Digital Library.

Description

The Waste Isolation Pilot Plant (WIPP) Recertification Project was established to meet the requirement of the WIPP Land Withdrawal Act (LWA)1 to demonstrate continued compliance with U.S. Environmental Protection Agency (EPA) disposal regulations at five-year intervals. This paper delineates the objective of the first recertification effort, sets out project goals, and establishes guiding assumptions. It describes the overall direction for a highly complex and interdependent set of tasks leading to recertification of the WIPP repository in 2004. This paper also lays out a high-level schedule for producing the WIPP Compliance Recertification Application (CRA). The major principle behind recertification is that the EPA recertification decision will not involve rulemaking or judicial review. To ensure that the EPA is able to retain this principle, the U.S. Department of Energy (DOE) will not be incorporating changes through the recertification process. Only changes previously approved by the EPA will be included in the CRA. The EPA can approve significant changes to the current WIPP Certification through rulemaking. Non-significant changes are approved without rulemaking through the planned change reporting process [Title 40 Code of Federal Regulations (CFR), Section 194.4(b)].

Physical Description

12 pages

Source

  • Waste Management 2002 Symposium, Tucson, AZ (US), 02/24/2002--02/28/2002

Language

Item Type

Identifier

Unique identifying numbers for this article in the Digital Library or other systems.

  • Report No.: none
  • Office of Scientific & Technical Information Report Number: 832711
  • Archival Resource Key: ark:/67531/metadc778670

Collections

This article is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this article?

When

Dates and time periods associated with this article.

Creation Date

  • February 25, 2002

Added to The UNT Digital Library

  • Dec. 3, 2015, 9:30 a.m.

Description Last Updated

  • Jan. 6, 2018, 8:55 p.m.

Usage Statistics

When was this article last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 11

Interact With This Article

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

International Image Interoperability Framework

IIF Logo

We support the IIIF Presentation API

Casey, S. C.; Shoemaker, P. E. & Patterson, R. L. Preparations and Planning for EPA Recertification of the Waste Isolation Pilot Plant, article, February 25, 2002; Tucson, Arizona. (digital.library.unt.edu/ark:/67531/metadc778670/: accessed October 20, 2018), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.