OPTIMIZATION OF MUD HAMMER DRILLING PERFORMANCE - A PROGRAM TO BENCHMARK THE VIABILITY OF ADVANCED MUD HAMMER DRILLING

PDF Version Also Available for Download.

Description

This document details the progress to date on the OPTIMIZATION OF MUD HAMMER DRILLING PERFORMANCE -- A PROGRAM TO BENCHMARK THE VIABILITY OF ADVANCED MUD HAMMER DRILLING contract for the quarter starting January 2001 through March 2001. Accomplishments to date include the following: (1) On January 9th of 2001, details of the Mud Hammer Drilling Performance Testing Project were presented at a ''kick-off'' meeting held in Morgantown. (2) A preliminary test program was formulated and prepared for presentation at a meeting of the advisory board in Houston on the 8th of February. (3) The meeting was held with the advisory ... continued below

Physical Description

13 pages

Creation Information

Tibbitts, Gordon & Judzis, Arnis April 1, 2001.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

This document details the progress to date on the OPTIMIZATION OF MUD HAMMER DRILLING PERFORMANCE -- A PROGRAM TO BENCHMARK THE VIABILITY OF ADVANCED MUD HAMMER DRILLING contract for the quarter starting January 2001 through March 2001. Accomplishments to date include the following: (1) On January 9th of 2001, details of the Mud Hammer Drilling Performance Testing Project were presented at a ''kick-off'' meeting held in Morgantown. (2) A preliminary test program was formulated and prepared for presentation at a meeting of the advisory board in Houston on the 8th of February. (3) The meeting was held with the advisory board reviewing the test program in detail. (4) Consensus was achieved and the approved test program was initiated after thorough discussion. (5) This new program outlined the details of the drilling tests as well as scheduling the test program for the weeks of 14th and 21st of May 2001. (6) All the tasks were initiated for a completion to coincide with the test schedule. (7) By the end of March the hardware had been designed and the majority was either being fabricated or completed. (8) The rock was received and cored into cylinders.

Physical Description

13 pages

Notes

OSTI as DE00809140

Source

  • Other Information: PBD: 1 Apr 2001

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Report No.: NONE
  • Grant Number: FC26-00NT40918
  • DOI: 10.2172/809140 | External Link
  • Office of Scientific & Technical Information Report Number: 809140
  • Archival Resource Key: ark:/67531/metadc740778

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • April 1, 2001

Added to The UNT Digital Library

  • Oct. 18, 2015, 6:40 p.m.

Description Last Updated

  • Jan. 3, 2017, 12:59 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 2

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

International Image Interoperability Framework

IIF Logo

We support the IIIF Presentation API

Tibbitts, Gordon & Judzis, Arnis. OPTIMIZATION OF MUD HAMMER DRILLING PERFORMANCE - A PROGRAM TO BENCHMARK THE VIABILITY OF ADVANCED MUD HAMMER DRILLING, report, April 1, 2001; United States. (digital.library.unt.edu/ark:/67531/metadc740778/: accessed July 17, 2018), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.