A271 GT-MHR COMMERCIALZATION STUDY TECHNICAL PROGRESS AND COST MANAGEMENT REPORT FOR THE PERIOD MAY 1 THROUGH MAY 31, 2003. Petten advised GA the start of the HFR-EU2 irradiation is being delayed until late July 2004. HFR-EU1 (pebble fuel) is also delayed until February/March 2004. The reason for the delays was implementation of new financial regulations at Petten that delayed the contracts for capsule fabrication. Review of the MHR-2 Fuel Product Specification was completed. Revision of the specification to incorporate the review results is in progress. Detailed test matrices have been drafted for capsule irradiation tests and for post-irradiation heating tests … continued below

Physical Description

8 pages

Creation Information

Shenoy, A. S. May 1, 2003.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by the UNT Libraries Government Documents Department to the UNT Digital Library, a digital repository hosted by the UNT Libraries. It has been viewed 26 times. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Author

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Titles

  • Added Title: GT-MHR Commercialzation Study Technical Progress and Cost Management Report for the Period May 1 Through May 31, 2003
  • Main Title: GT-MHR Commercialization Study Technical Progress and Cost Management Report: May 2003
  • Serial Title: GT-MHR Commercialization StudyProgress Report

Description

A271 GT-MHR COMMERCIALZATION STUDY TECHNICAL PROGRESS AND COST MANAGEMENT REPORT FOR THE PERIOD MAY 1 THROUGH MAY 31, 2003. Petten advised GA the start of the HFR-EU2 irradiation is being delayed until late July 2004. HFR-EU1 (pebble fuel) is also delayed until February/March 2004. The reason for the delays was implementation of new financial regulations at Petten that delayed the contracts for capsule fabrication. Review of the MHR-2 Fuel Product Specification was completed. Revision of the specification to incorporate the review results is in progress. Detailed test matrices have been drafted for capsule irradiation tests and for post-irradiation heating tests proposed for development and qualification of advanced coated-particle fuels capable of meeting anticipated VHTR fuel performance requirements.

Physical Description

8 pages

Notes

INIS; OSTI as DE00814890

Source

  • Other Information: PBD: 1 May 2003

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • May 1, 2003

Added to The UNT Digital Library

  • Oct. 18, 2015, 6:40 p.m.

Description Last Updated

  • July 10, 2019, 6:06 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 26

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

International Image Interoperability Framework

IIF Logo

We support the IIIF Presentation API

Shenoy, A. S. GT-MHR Commercialization Study Technical Progress and Cost Management Report: May 2003, report, May 1, 2003; United States. (https://digital.library.unt.edu/ark:/67531/metadc740258/: accessed June 9, 2023), University of North Texas Libraries, UNT Digital Library, https://digital.library.unt.edu; crediting UNT Libraries Government Documents Department.

Back to Top of Screen