Post-Closure Inspection Report for Corrective Action Unit 407: Roller Coaster RadSafe Area Tonopah Test Range, Nevada, Calendar Year 2001

PDF Version Also Available for Download.

Description

Post-closure monitoring requirements for the Roller Coaster RadSafe Area (Corrective Action Unit [CAU] 407) (Figure 1) are described in Closure Report for Corrective Action Unit 407, Roller Coaster RadSafe Area, Tonopah Test Range, Nevada, report number DOEN-694, October 2001. The Closure Report (CR) was submitted to the Nevada Division of Environmental Protection (NDEP) on April 24,2001. No issues with the post-closure monitoring plan, Section 5 .O, were raised. However, other concerns raised by stakeholders required that the CR be revised. Revision 1 of CR was issued in December of 2001 and was approved by NDEP on January 7,2002. Section 5.2 ... continued below

Physical Description

vp.

Creation Information

Campbell, K. B. January 1, 2002.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

Post-closure monitoring requirements for the Roller Coaster RadSafe Area (Corrective Action Unit [CAU] 407) (Figure 1) are described in Closure Report for Corrective Action Unit 407, Roller Coaster RadSafe Area, Tonopah Test Range, Nevada, report number DOEN-694, October 2001. The Closure Report (CR) was submitted to the Nevada Division of Environmental Protection (NDEP) on April 24,2001. No issues with the post-closure monitoring plan, Section 5 .O, were raised. However, other concerns raised by stakeholders required that the CR be revised. Revision 1 of CR was issued in December of 2001 and was approved by NDEP on January 7,2002. Section 5.2 of the NDEP-approved CR calls for site inspections to be conducted within the first six months following completion of cover construction. Following the first six months, site inspection are to be conducted twice yearly for the next two years. This report provides the results of the six month post-construction site inspection. As stated in Section 5.2 of the CR, Post-closure site inspections at CAU 407 consists of the following: (1) Visual site inspections done twice a year to evaluate the condition of the cover and plant development. (2) Verification that the site is secure and condition of the fence and posted warning signs. (3) Notice of any subsidence, erosion, unauthorized excavation, etc., deficiencies that may compromise the integrity of the unit. (4) Remedy of any deficiencies within 90 days of discovery. (5) Preparation and submittal of an annual report. To meet the fiscal year 2002 post-closure inspection schedule, the first post-closure site inspection was conducted on November 6,2001. The site inspection was conducted after completion of the revegetation activities (October 24,2000) and submittal of revision 0 of the CR (October 31,2001). All site inspections were conducted in accordance with the Post-Closure Inspection requirements stated in revision 0 of the CR. This report includes copies of inspection checklist, photographs, recommendations, and conclusions. The Post-Closure Inspection Checklist is found in Attachment A, a copy of the field notes is found in Attachment By and copies of the inspection photographs are found in Attachment C.

Physical Description

vp.

Notes

OSTI as DE00797306

Source

  • Other Information: PBD: 1 Jan 2002

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Report No.: DOE/NV--793
  • Grant Number: AC08-96NV11718
  • DOI: 10.2172/797306 | External Link
  • Office of Scientific & Technical Information Report Number: 797306
  • Archival Resource Key: ark:/67531/metadc739381

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • January 1, 2002

Added to The UNT Digital Library

  • Oct. 19, 2015, 7:39 p.m.

Description Last Updated

  • Feb. 15, 2016, 11:41 a.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 5

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Campbell, K. B. Post-Closure Inspection Report for Corrective Action Unit 407: Roller Coaster RadSafe Area Tonopah Test Range, Nevada, Calendar Year 2001, report, January 1, 2002; Nevada. (digital.library.unt.edu/ark:/67531/metadc739381/: accessed September 22, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.