System Configuration Management Implementation Procedure for the Canister Storage Building (CSB) Page: 2 of 32
This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided to UNT Digital Library by the UNT Libraries Government Documents Department.
Extracted Text
The following text was automatically extracted from the image on this page using optical character recognition software:
E. ECN (use no. from pg. 1)
ENGINEERING CHANGE NOTICEPaeo2634
Page 2 of 2 663443
16. Design 17. Cost Impact 18. Schedule Impact (days)
Verification
Required
ENGINEERING CONSTRUCTION
[x] Yes Additional [ I N/A Additional [ ] Improvement [] N/A
[ ] No Savings [ ] Savings [] Delay []
19. Change Impact Review: Indicate the related documents (other than the engineering documents identified on Side 1) that will be affected by the change
described in Block 13. Enter the affected document number in Block 20.
SDD/DD [] N/A Seijmic/Strea Analysia [] Tank Calibration Manual
Functional Design Criteria Stress/esign Report Health Physics Procedure []
Operating Specification Interface Control Drawing [] Spares Multiple Unit Listing []
Criticality Specifticaion Calibration Procedure [] Test Procedurms/Specification []
Conceptual Design Report [] Installation Procedure [] Component lodex
Equipment Spec. Maintenance Procedure [] ASME Coded Item
Const. Spec. [ Engineertag Procedure [] Hunan Factor Consideration
Procurenent Spec. Operating Instruction [] Corrpmler Software
Vendor Information [] Operating Procedure [] Electric Circuit Schedule
OM Manual [1 Operational Safety Requirement ICRS Procedure
FSAR/SAR [] JEFD Drawing [] Process Control Manual/Plan
Safety Equipment List [ Cell Arrangement Drawing [] Pocess Flow Chart
Radiation Work Pertait [] Essential Material Specification [l Purchase Requisition
Environmental lnpct Statement []Fac. Poc. Samp. Schedule [] Tickler File
Environmental Report [] inspection Plan [] []
Environmental Permit [] Inventory Adjustmem Request
20. Other Affected Documents: (NOTE: Documents listed below will not be revised by this ECN.) Signatures below indicate that the signing organization has
been notified of other affected documents listed below.
Document Number/Revision Document Number/Revision Document Number Revision
N/A
21. Approvals
Signature Date Signature Date
CSB Design Authority S. A. Kreig 4&O16Vtt.
Cog Eng R. C. Garrison
Cog Mgr G. D. Bazinet //t
QA S. S. Moss
Safety L. J. Garvin
DEPARTMENT OF ENERGY
Signature or a Control Number that tracks the N/A
Approval Signature
ADDITIONALA-7900-013-3 (05/96) GEF096
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
GARRISON, R.C. System Configuration Management Implementation Procedure for the Canister Storage Building (CSB), report, November 28, 2000; United States. (https://digital.library.unt.edu/ark:/67531/metadc737417/m1/2/: accessed April 19, 2024), University of North Texas Libraries, UNT Digital Library, https://digital.library.unt.edu; crediting UNT Libraries Government Documents Department.