Engineering task plan for the development of a high pressure water drill system for BY-105 saltwell screen installation

PDF Version Also Available for Download.

Description

This engineering task plan identifies the activities required for developing an ultra high pressure water drill system for installation of a saltwell screen in Tank BY-105. A water drill system is needed to bore through the hard waste material in this tank because of the addition of Portland cement in the 1960s and/or 1970s. The activities identified in this plan include the design, procurement, and qualification testing of the water drill along with readiness preparations including developing operating procedures, training Operations personnel, and conducting an assessment of readiness.

Physical Description

38 pages

Creation Information

RITTER, G.A. February 24, 1999.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Author

Sponsor

Publisher

  • Hanford Site (Wash.)
    Publisher Info: HNF Hanford Site (United States)
    Place of Publication: United States

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

This engineering task plan identifies the activities required for developing an ultra high pressure water drill system for installation of a saltwell screen in Tank BY-105. A water drill system is needed to bore through the hard waste material in this tank because of the addition of Portland cement in the 1960s and/or 1970s. The activities identified in this plan include the design, procurement, and qualification testing of the water drill along with readiness preparations including developing operating procedures, training Operations personnel, and conducting an assessment of readiness.

Physical Description

38 pages

Notes

INIS; OSTI as DE00781545

Source

  • Other Information: PBD: 24 Feb 1999

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Report No.: HNF--3225--REV0
  • Report No.: EW3120071
  • Grant Number: AC06-96RL13200
  • DOI: 10.2172/781545 | External Link
  • Office of Scientific & Technical Information Report Number: 781545
  • Archival Resource Key: ark:/67531/metadc717149

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • February 24, 1999

Added to The UNT Digital Library

  • Sept. 29, 2015, 5:31 a.m.

Description Last Updated

  • April 27, 2016, 4:11 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 2
Total Uses: 9

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

RITTER, G.A. Engineering task plan for the development of a high pressure water drill system for BY-105 saltwell screen installation, report, February 24, 1999; United States. (digital.library.unt.edu/ark:/67531/metadc717149/: accessed August 21, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.