This paper describes the wind-diesel hybrid power project, a technology demonstration project conducted by the National Renewable Energy Laboratory, Kotzebue Electric Association, the Alaska Village Electric Cooperative and the Alaska Energy Authority in Wales, Alaska. It discusses each of the relevant plant design considerations in detail, in hopes that system integrators and project planners that read the report will realize the importance of giving proper attention to diesel plant preparation (or replacement), and future wind-diesel systems will be installed and commissioned more quickly and cost effectively.

Physical Description

vp.

Creation Information

Drouilhet, S. August 2, 2001.

Context

This article is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. It has been viewed 14 times . More information about this article can be viewed below.

Who

People and organizations associated with either the creation of this article or its content.

Author

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this article. Follow the links below to find similar items on the Digital Library.

Description

This paper describes the wind-diesel hybrid power project, a technology demonstration project conducted by the National Renewable Energy Laboratory, Kotzebue Electric Association, the Alaska Village Electric Cooperative and the Alaska Energy Authority in Wales, Alaska. It discusses each of the relevant plant design considerations in detail, in hopes that system integrators and project planners that read the report will realize the importance of giving proper attention to diesel plant preparation (or replacement), and future wind-diesel systems will be installed and commissioned more quickly and cost effectively.

Physical Description

vp.

Source

  • AWEA's WINDPOWER 2001 Conference, Washington, DC (US), 06/04/2001--06/07/2001

Language

Item Type

Identifier

Unique identifying numbers for this article in the Digital Library or other systems.

  • Report No.: NREL/CP-500-30586
  • Grant Number: AC36-99GO10337
  • Office of Scientific & Technical Information Report Number: 786356
  • Archival Resource Key: ark:/67531/metadc715877

Collections

This article is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

What responsibilities do I have when using this article?

When

Dates and time periods associated with this article.

Creation Date

  • August 2, 2001

Added to The UNT Digital Library

  • Sept. 29, 2015, 5:31 a.m.

Description Last Updated

  • March 31, 2016, 8:26 p.m.

Usage Statistics

When was this article last used?

Yesterday: 0
Past 30 days: 1
Total Uses: 14

Interact With This Article

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Drouilhet, S. Preparing an Existing Diesel Power Plant for a Wind Hybrid Retrofit: Lessons Learned in the Wales, Alaska, Wind-Diesel Hybrid Power Project, article, August 2, 2001; Golden, Colorado. (digital.library.unt.edu/ark:/67531/metadc715877/: accessed August 23, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.