Site management system executive summary report -- March 1995

PDF Version Also Available for Download.

Description

Performance data for March 1995 reflects a continued unfavorable schedule variance and favorable cost variance. The March fiscal-year-to-date (FYTD) schedule variance is an unfavorable $105.5M. EM-30 (Office of Waste Management) is the biggest contributor ($81.9 million) to the behind-schedule condition. The majority of the EM-30 schedule variance is associated with the Tank Waste Remediation System (TWRS) program. A breakdown of individual program performance is listed on page 6. The TWRS schedule variance totals a negative $63.0 million and is attributed to the delay in receiving key decision 0 (KD-0) for Project W-314, {open_quotes}Tank Farm Restoration and Safe Operations{close_quotes}; the delay ... continued below

Physical Description

35 p.

Creation Information

Schultz, E.A. March 1, 1995.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Author

Sponsor

Publisher

  • Westinghouse Hanford Company
    Publisher Info: Westinghouse Hanford Co., Richland, WA (United States)
    Place of Publication: Richland, Washington

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

Performance data for March 1995 reflects a continued unfavorable schedule variance and favorable cost variance. The March fiscal-year-to-date (FYTD) schedule variance is an unfavorable $105.5M. EM-30 (Office of Waste Management) is the biggest contributor ($81.9 million) to the behind-schedule condition. The majority of the EM-30 schedule variance is associated with the Tank Waste Remediation System (TWRS) program. A breakdown of individual program performance is listed on page 6. The TWRS schedule variance totals a negative $63.0 million and is attributed to the delay in receiving key decision 0 (KD-0) for Project W-314, {open_quotes}Tank Farm Restoration and Safe Operations{close_quotes}; the delay in receiving KD-3 for Project W-320, {open_quotes}106-C Sluicing{close_quotes}; late deployment of the rotary and push mode sampling trucks due to equipment and operational issues; late placement of melter contracts; and the Multi-Function Waste Tank Facility (MWTF) workscope still being a part of the baseline. Class I change requests are in process to rebaseline the activities associated with KDs. An aggressive sampling schedule has been developed for the rotary and push mode sampling activity. Thirty-seven enforceable agreement milestones were schedule FYTD. Thirty-six (97 percent) of the thirty-seven were completed on or ahead of schedule and one (3 percent) is delinquent. The Department of Energy, Richland Operations Office entered into dispute resolution on April 7, 1995, for the delinquent milestone. Six (13 percent) of the 39 remaining enforceable agreement milestones scheduled for FY 1995 are forecast to be late. Additional information on these milestones can be found on pages 13 through 15. Performance data reflects a significant favorable $25.7 million (4 percent) cost variance. The majority of the cost variance is attributed to progress towards achievement of productivity commitment goals and is expected to continue for the remainder of this fiscal year.

Physical Description

35 p.

Notes

INIS; OSTI as DE95013581

Source

  • Other Information: PBD: Mar 1995

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Other: DE95013581
  • Report No.: WHC-SP--0969-48
  • Grant Number: AC06-87RL10930
  • DOI: 10.2172/79058 | External Link
  • Office of Scientific & Technical Information Report Number: 79058
  • Archival Resource Key: ark:/67531/metadc715040

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • March 1, 1995

Added to The UNT Digital Library

  • Sept. 29, 2015, 5:31 a.m.

Description Last Updated

  • Feb. 8, 2016, 9:32 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 6

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Schultz, E.A. Site management system executive summary report -- March 1995, report, March 1, 1995; Richland, Washington. (digital.library.unt.edu/ark:/67531/metadc715040/: accessed December 12, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.