The Tokamak Fusion Test Reactor (TFTR) ceased operation in April 1997 and decommissioning commenced in October 1999. The deuterium-tritium fusion experiments resulted in contaminating the vacuum vessel with tritium and activating the materials with 14 Mev neutrons. The total tritium content within the vessel is in excess of 7,000 Curies while dose rates approach 50 mRem/hr. These radiological hazards along with the size of the Tokamak (100 cubic meters) present a unique and challenging task for dismantling. Plasma arc cutting is the current baseline technology for the dismantlement of fission reactors. This technology is typically used because of its faster ... continued below

Physical Description

220 Kilobytes pages

Creation Information

Rule, K.; Perry, E.; Larson, S. & Viola, M. February 24, 2000.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

The Tokamak Fusion Test Reactor (TFTR) ceased operation in April 1997 and decommissioning commenced in October 1999. The deuterium-tritium fusion experiments resulted in contaminating the vacuum vessel with tritium and activating the materials with 14 Mev neutrons. The total tritium content within the vessel is in excess of 7,000 Curies while dose rates approach 50 mRem/hr. These radiological hazards along with the size of the Tokamak (100 cubic meters) present a unique and challenging task for dismantling. Plasma arc cutting is the current baseline technology for the dismantlement of fission reactors. This technology is typically used because of its faster cutting times. Alternatively, an innovative approach for dismantlement of the TFTR is the use of diamond wire cutting technology. Recent improvements in diamond wire technology have allowed the cutting of carbon steel components such as pipe, plate, and tube bundles in heat exchangers. Some expected benefits of this technology include: significantly reduction in airborne contaminates, reduced personnel exposure, a reduced risk of spread of tritium contamination, and reduced overall costs as compared to using plasma arc cutting. This paper will provide detailed results of the diamond wire cutting demonstration that was completed in September of 1999, on a mock-up of this complex reactor. The results will identify cost, safety, industrial and engineering parameters, and the related performance of each situation.

Physical Description

220 Kilobytes pages

Notes

INIS; OSTI as DE00751586

Source

  • Other Information: PBD: 24 Feb 2000

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Report No.: PPPL--3439
  • Grant Number: AC02-76CH03073
  • DOI: 10.2172/751586 | External Link
  • Office of Scientific & Technical Information Report Number: 751586
  • Archival Resource Key: ark:/67531/metadc712414

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • February 24, 2000

Added to The UNT Digital Library

  • Sept. 12, 2015, 6:31 a.m.

Description Last Updated

  • April 15, 2016, 7:19 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 3

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Rule, K.; Perry, E.; Larson, S. & Viola, M. Demonstrating diamond wire cutting of the TFTR, report, February 24, 2000; Princeton, New Jersey. (digital.library.unt.edu/ark:/67531/metadc712414/: accessed December 15, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.