Description

This report describes the first year of a 3-year PVMaT Phase 5A2 program. Evergreen Solar will soon be expanding into a multi-megawatt facility and the PVMaT work will be used to further the objective of a high-throughput automated production line in every aspect of PV module making from producing silicon ribbon to making a finished module. The project has four task areas for this first year: crystal growth; cell manufacturing; modules; and factory layout and automation. The vast majority of the work this first year has been in the crystal growth and cell manufacturing areas. Evergreen Solar has its own ... continued below

Physical Description

vp.

Creation Information

Hanoka, J. I. November 3, 1999.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Author

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

This report describes the first year of a 3-year PVMaT Phase 5A2 program. Evergreen Solar will soon be expanding into a multi-megawatt facility and the PVMaT work will be used to further the objective of a high-throughput automated production line in every aspect of PV module making from producing silicon ribbon to making a finished module. The project has four task areas for this first year: crystal growth; cell manufacturing; modules; and factory layout and automation. The vast majority of the work this first year has been in the crystal growth and cell manufacturing areas. Evergreen Solar has its own unique technology in each of these areas. In crystal growth, a key goal of this PVMaT project has been developing and deploying an improved string material. The high-temperature string materials are used to stabilize the edges of the growing silicon ribbon in the String Ribbon silicon sheet growth. The result has been one of the major successes of this first year. Significant cost reductions and yield improvements have emerged from this improved string material. In addition, some of the groundwork for automation of the String Ribbon crystal growth process has been laid and shows much promise. A method for controlling the edge meniscus height was developed, and a patent has been filed based on this discovery. In the cell manufacturing area, the focus has been on reducing the number of processing steps and on design and construction of high-speed processing equipment. The possibility of eliminating all pre-diffusion etching and going directly from growth to diffusion has been demonstrated on an R and D scale. Unique designs for high-speed drying equipment and for a high-speed contact and AR-coating application machine have been developed. In the latter case, the basic concepts underlying various aspects of the machine design have been successfully tested for viability. The integration of the different components of this machine into a smoothly working whole is now well under way. In addition, nonvacuum methods of hydrogen passivation have been investigated, but no production-viable process has emerged from this work. In the module area, initial work has shown that the unique properties of the backskin developed under Evergreen's earlier PVMaT Phase 4A1 contract can be expected to make the lay-up process simpler and involve less labor. For factory layout and automation, the authors have enlisted the Fraunhofer Manufacturing Institute at Boston University to aid them with the layout and process flow of their new factory. In general, the project is on schedule, with no significant technical barriers to reach their ultimate objectives.

Physical Description

vp.

Source

  • Other Information: PBD: 3 Nov 1999

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Report No.: NREL/SR--520-26891
  • Grant Number: AC36-99GO10337
  • DOI: 10.2172/752411 | External Link
  • Office of Scientific & Technical Information Report Number: 752411
  • Archival Resource Key: ark:/67531/metadc705667

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • November 3, 1999

Added to The UNT Digital Library

  • Sept. 12, 2015, 6:31 a.m.

Description Last Updated

  • March 28, 2016, 12:07 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 5

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Hanoka, J. I. Continuous, automated manufacturing of string ribbon Si PV modules. PVMaT Phase 5A2 Subcontract: First Annual Report, 21 May 1998--20 May 1999, report, November 3, 1999; Golden, Colorado. (digital.library.unt.edu/ark:/67531/metadc705667/: accessed August 19, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.