At the request of the Western Area Power Administration (Western), an audit of 17 areas was conducted with respect to possible overcharges on a power contract between Western and Basin Electric Power Cooperative (Basin), Contract No. DE-MP65-82WP-19001. The contract for Western`s purchase of electric power from Basin was entered into on April 15, 1982, and was in effect from January 1, 1986, through October 31, 1990. During this 58-month period, Basin billed Western approximately $197.6 million. Overall, it was found that Basin overcharged Western approximately $23.8 million. These overcharges occurred because Basin: (1) did not recognize or amortize as gain …
continued below
Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.
Descriptive information to help identify this report.
Follow the links below to find similar items on the Digital Library.
Description
At the request of the Western Area Power Administration (Western), an audit of 17 areas was conducted with respect to possible overcharges on a power contract between Western and Basin Electric Power Cooperative (Basin), Contract No. DE-MP65-82WP-19001. The contract for Western`s purchase of electric power from Basin was entered into on April 15, 1982, and was in effect from January 1, 1986, through October 31, 1990. During this 58-month period, Basin billed Western approximately $197.6 million. Overall, it was found that Basin overcharged Western approximately $23.8 million. These overcharges occurred because Basin: (1) did not recognize or amortize as gain its overestimate of completion and correction costs for Antelope Valley Station (AVS) Unit 2; (2) did not amortize the gain on the sale/leaseback of AVS Unit 2 as an offset to lease costs; (3) billed Western prematurely for lease and interest costs; (4) overcharged for the cost of coal by including administrative and general expenses and profit, as well as incorrectly calculating discounts, royalty payments, and imputed interest costs; (5) made faulty calculations of amortization rates for deferred costs; (6) used a shorter depreciation period for AVS common facilities than it had used for other power plants; (7) retained tax benefit transfers; and (8) charged Western for interest and depreciation that had been paid by others. In addition to the $23.8 million in overcharges, interest accrued on the overcharges through December 31, 1996 was estimated to be approximately $22.1 million, resulting in a total of $45.9 million due Western.
This report is part of the following collection of related materials.
Office of Scientific & Technical Information Technical Reports
Reports, articles and other documents harvested from the Office of Scientific and Technical Information.
Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.
Office of Inspector General report on audit of the Western Area Power Administration`s contract with Basin Electric Power Cooperative,
report,
June 25, 1997;
United States.
(https://digital.library.unt.edu/ark:/67531/metadc680840/:
accessed April 17, 2024),
University of North Texas Libraries, UNT Digital Library, https://digital.library.unt.edu;
crediting UNT Libraries Government Documents Department.