The Western Area Power Administration is proposing to rebuild a 3.0 mile segment of the existing Flatiron-Weld 115-kV transmission line in Weld County. The line would be reconductored with new conductor on new wood pole double circuit structures. The new structures would support a double circuit transmission line configuration. The first circuit would be owned by Western and the second by Public Service Company of Colorado (PSCO). Alternatives considered included no action, constructing PSCO`s circuit on new right-of-way, and reconductoring Western`s existing line on the same structures. The proposed action was selected because it provided an opportunity to share structures ... continued below

Physical Description

47 p.

Creation Information

Creator: Unknown. May 1, 1996.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Creator

  • We've been unable to identify the creator(s) of this report.

Sponsor

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

The Western Area Power Administration is proposing to rebuild a 3.0 mile segment of the existing Flatiron-Weld 115-kV transmission line in Weld County. The line would be reconductored with new conductor on new wood pole double circuit structures. The new structures would support a double circuit transmission line configuration. The first circuit would be owned by Western and the second by Public Service Company of Colorado (PSCO). Alternatives considered included no action, constructing PSCO`s circuit on new right-of-way, and reconductoring Western`s existing line on the same structures. The proposed action was selected because it provided an opportunity to share structures with PSCO and, overall, would minimize costs and environmental impacts. The environmental assessment identifies minor effects on existing natural or human resources and minor benefits for agricultural operations.

Physical Description

47 p.

Notes

INIS; OSTI as DE97000266

Source

  • Other Information: PBD: May 1996

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Other: DE97000266
  • Report No.: DOE/EA--1095
  • DOI: 10.2172/380344 | External Link
  • Office of Scientific & Technical Information Report Number: 380344
  • Archival Resource Key: ark:/67531/metadc677649

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • May 1, 1996

Added to The UNT Digital Library

  • July 25, 2015, 2:20 a.m.

Description Last Updated

  • June 24, 2016, 1:59 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 3
Total Uses: 7

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

International Image Interoperability Framework

IIF Logo

We support the IIIF Presentation API

Weld-Windsor 115-kV Transmission Line Project, Weld County, Colorado, report, May 1, 1996; United States. (digital.library.unt.edu/ark:/67531/metadc677649/: accessed December 11, 2018), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.