Description

The acceptance inspection of construction by Fluor Daniel Hanford (FDH) is performed to provide assurance that fabrication, construction, and installation are in accordance with approved contract documents. Approved contract documents used to perform inspections may include specifications, drawings, and contractor submittals such as fabrication drawings, procedures, etc. The amount or degree of inspection activity is tailored to the project as determined by the project team so that the effort and cost expended are commensurate with the importance of the facility in terms of function and safety. Inspections are documented to provide verification of the acceptability of the work performed. This ... continued below

Physical Description

12 p.

Creation Information

Shen, E.J. January 9, 1998.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Author

Sponsor

Publisher

  • Fluor Daniel Hanford, Inc.
    Publisher Info: Fluor Daniel Hanford, Inc., Richland, WA (United States)
    Place of Publication: Richland, Washington

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

The acceptance inspection of construction by Fluor Daniel Hanford (FDH) is performed to provide assurance that fabrication, construction, and installation are in accordance with approved contract documents. Approved contract documents used to perform inspections may include specifications, drawings, and contractor submittals such as fabrication drawings, procedures, etc. The amount or degree of inspection activity is tailored to the project as determined by the project team so that the effort and cost expended are commensurate with the importance of the facility in terms of function and safety. Inspections are documented to provide verification of the acceptability of the work performed. This document identifies the inspections and documentation forms to be provided. It is prepared and implemented with the understanding that the construction contractor is fully responsible for compliance with contract documents and for the quality of work performed. Inspections performed are in accordance with approved procedures. The Manager of Acceptance Inspection is responsible for the implementation of this plan and assignment of personnel for the work. Inspections are conducted by personnel who are qualified and certified, to perform their assigned task. The Acceptance Inspection Plan is organized in the Construction Specification Institute (CSI) format to cross reference design specification sections with sections of the AI Plan. In each AI Plan section the applicable specification section subject will be identified followed by the appropriate inspection requirements. General surveillances will be listed when applicable. Acceptance Inspection Reports are provided to document inspections not documented on a test report (i.e., Soil Test Data, Concrete Test Report, NDE/Weld Record, Leak/Pressure Test Certification, Backflow Device Test Report, Nonconformance Report, Deficiency Report, and/or Contractors testing forms).

Physical Description

12 p.

Notes

INIS; OSTI as DE99050448

Source

  • Other Information: PBD: 9 Jan 1998

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Other: DE99050448
  • Report No.: HNF--2064
  • Grant Number: AC06-96RL13200
  • DOI: 10.2172/362396 | External Link
  • Office of Scientific & Technical Information Report Number: 362396
  • Archival Resource Key: ark:/67531/metadc677188

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • January 9, 1998

Added to The UNT Digital Library

  • July 25, 2015, 2:20 a.m.

Description Last Updated

  • June 14, 2016, 1:49 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 2

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Shen, E.J. Acceptance inspection plan 105KE Facility modifications for fuel retrieval subproject, report, January 9, 1998; Richland, Washington. (digital.library.unt.edu/ark:/67531/metadc677188/: accessed November 23, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.