A gyrotron producing nominally 1 MW at 110 GHz has been installed at the DIII-D tokamak and operated in a program of initial tests with a windowless evacuated transmission line. The alignment and first test operation were performed in an air environment at atmospheric pressure. Under these conditions, the tube produced rf output in excess of 800 kW for pulse lengths greater than 10 msec and power near 500 kW for pulse lengths of about 100 msec into a free space dummy load. The gyrotron was operated into evacuated corrugated waveguide in the full power parameter regime for pulse lengths ... continued below

Physical Description

20 p.

Creation Information

Lohr, J.; Ponce, D. & Tooker, J.F. August 1, 1996.

Context

This article is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this article can be viewed below.

Who

People and organizations associated with either the creation of this article or its content.

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this article. Follow the links below to find similar items on the Digital Library.

Description

A gyrotron producing nominally 1 MW at 110 GHz has been installed at the DIII-D tokamak and operated in a program of initial tests with a windowless evacuated transmission line. The alignment and first test operation were performed in an air environment at atmospheric pressure. Under these conditions, the tube produced rf output in excess of 800 kW for pulse lengths greater than 10 msec and power near 500 kW for pulse lengths of about 100 msec into a free space dummy load. The gyrotron was operated into evacuated corrugated waveguide in the full power parameter regime for pulse lengths of up to 500 msec injecting greater than 0.5 MW into DIII-D for a preliminary series of experiments. Generated powers greater than 900 kW were achieved. A parasitic oscillation at various frequencies between 20 and 100 MHz, which was generated during the pulsing of the gyrotron electron beam, was suppressed somewhat by a capacitive filter attached to the gyrotron itself. Addition of a magnetic shield intended to alter the magnetic field geometry below the cathode eliminated internal tube sparks. Rework of the external power and interlock circuitry to improve the immunity to electromagnetic interference was also done in parallel so that the fast interlock circuitry could be used. The latest results of the test program, the design of the free space load and other test hardware, and the transmission line will be presented.

Physical Description

20 p.

Notes

INIS; OSTI as DE97003031

Source

  • 3. international workshop on strong microwaves in plasmas, Moscow/St. Petersburg (Russian Federation), 7-14 Aug 1996

Language

Item Type

Identifier

Unique identifying numbers for this article in the Digital Library or other systems.

  • Other: DE97003031
  • Report No.: GA--A22420
  • Report No.: CONF-9608188--1
  • Grant Number: AC03-89ER51114
  • Office of Scientific & Technical Information Report Number: 442153
  • Archival Resource Key: ark:/67531/metadc676520

Collections

This article is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

What responsibilities do I have when using this article?

When

Dates and time periods associated with this article.

Creation Date

  • August 1, 1996

Added to The UNT Digital Library

  • July 25, 2015, 2:21 a.m.

Description Last Updated

  • Nov. 6, 2015, 12:21 p.m.

Usage Statistics

When was this article last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 5

Interact With This Article

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Lohr, J.; Ponce, D. & Tooker, J.F. Initial tests and operation of a 110 GHz, 1 MW gyrotron with evacuated waveguide system on the DIII-D tokamak, article, August 1, 1996; United States. (digital.library.unt.edu/ark:/67531/metadc676520/: accessed August 21, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.