The Advanced Test Reactor probabilistic risk assessment for internal fire and flood events defined a relatively high risk for a total loss of electric power possibly leading to core damage. Backup power sources were disabled due to fire and flooding in the diesel generator area with propagation of the flooding to a common switchgear room. The ATR risk assessment was employed to define options for relocation of backup power system components to achieve needed risk reduction while minimizing costs. The risk evaluations were performed using sensitivity studies and importance measures. The risk-based evaluations of relocation options for backup power systems ... continued below

Physical Description

10 p.

Creation Information

Atkinson, S.A. October 1, 1995.

Context

This article is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this article can be viewed below.

Who

People and organizations associated with either the creation of this article or its content.

Sponsor

Publisher

  • EG & G, Inc.
    Publisher Info: EG and G Idaho, Inc., Idaho Falls, ID (United States)
    Place of Publication: Idaho Falls, Idaho

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this article. Follow the links below to find similar items on the Digital Library.

Description

The Advanced Test Reactor probabilistic risk assessment for internal fire and flood events defined a relatively high risk for a total loss of electric power possibly leading to core damage. Backup power sources were disabled due to fire and flooding in the diesel generator area with propagation of the flooding to a common switchgear room. The ATR risk assessment was employed to define options for relocation of backup power system components to achieve needed risk reduction while minimizing costs. The risk evaluations were performed using sensitivity studies and importance measures. The risk-based evaluations of relocation options for backup power systems saved over $3 million from what might have been otherwise considered {open_quotes}necessary{close_quotes} for safety/risk improvement. The ATR experience shows that the advantages of a good risk assessment are to define risk significance, risk specifics, and risk solutions which enable risk goals to be achieved at the lowest cost.

Physical Description

10 p.

Notes

INIS; OSTI as DE96001711

Source

  • 1995 International mechanical engineering congress and exhibition, San Francisco, CA (United States), 12-17 Nov 1995

Language

Item Type

Identifier

Unique identifying numbers for this article in the Digital Library or other systems.

  • Other: DE96001711
  • Report No.: INEL--95/00275
  • Report No.: CONF-951135--21
  • Grant Number: AC07-94ID13223
  • Office of Scientific & Technical Information Report Number: 116705
  • Archival Resource Key: ark:/67531/metadc624113

Collections

This article is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

What responsibilities do I have when using this article?

When

Dates and time periods associated with this article.

Creation Date

  • October 1, 1995

Added to The UNT Digital Library

  • June 16, 2015, 7:43 a.m.

Description Last Updated

  • April 26, 2016, 4:46 p.m.

Usage Statistics

When was this article last used?

Yesterday: 0
Past 30 days: 1
Total Uses: 9

Interact With This Article

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Atkinson, S.A. Achieving safety/risk goals for less ATR backup power upgrades, article, October 1, 1995; Idaho Falls, Idaho. (digital.library.unt.edu/ark:/67531/metadc624113/: accessed September 24, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.