The x-ray radiation shielding requirements beyond the first optics enclosure have been considered for the beam transport of the 2-ID-B and 2-ID-C branch lines of Sector 2 (SRI-CAT) of the APS. The first three optical components (mirrors) of the 2-ID-B branch are contained within the shielded first optics enclosure. Calculations indicate that scattering of the primary synchrotron beam by beamline components outside the enclosure, such as apertures and monochromators, or by gas particles in case of vacuum failure is within safe limits for this branch. A standard 2.5-inch-diameter stainless steel pipe with 1/16-inch-thick walls provides adequate shielding to reduce the ... continued below

Physical Description

29 p.

Creation Information

Feng, Y.P.; Lai, B.; McNulty, I.; Dejus, R.J.; Randall, K.J. & Yun, W. August 1, 1995.

Context

This report is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

The x-ray radiation shielding requirements beyond the first optics enclosure have been considered for the beam transport of the 2-ID-B and 2-ID-C branch lines of Sector 2 (SRI-CAT) of the APS. The first three optical components (mirrors) of the 2-ID-B branch are contained within the shielded first optics enclosure. Calculations indicate that scattering of the primary synchrotron beam by beamline components outside the enclosure, such as apertures and monochromators, or by gas particles in case of vacuum failure is within safe limits for this branch. A standard 2.5-inch-diameter stainless steel pipe with 1/16-inch-thick walls provides adequate shielding to reduce the radiation dose equivalent rate to human tissue to below the maximum permissible limit of 0.25 mrem/hr. The 2-ID-C branch requires, between the first optics enclosure where only two mirrors are used and the housing for the third mirror, additional lead shielding (0.75 mm) and a minimum approach distance of 2.6 cm. A direct beam stop consisting of at least 4.5 mm of lead is also required immediately downstream of the third mirror for 2-ID-C. Finally, to stop the direct beam from escaping the experimental station, a beam stop consisting of at least 4-mm or 2.5-mm steel is required for the 2-ID-B or 2-ID-C branches, respectively. This final requirement can be met by the vacuum chambers used to house the experiments for both branch lines.

Physical Description

29 p.

Notes

INIS; OSTI as DE96002285

Source

  • Other Information: PBD: 1 Aug 1995

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Other: DE96002285
  • Report No.: LS--251(ANL)
  • Grant Number: W-31109-ENG-38
  • DOI: 10.2172/132728 | External Link
  • Office of Scientific & Technical Information Report Number: 132728
  • Archival Resource Key: ark:/67531/metadc620416

Collections

This report is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • August 1, 1995

Added to The UNT Digital Library

  • June 16, 2015, 7:43 a.m.

Description Last Updated

  • Dec. 15, 2015, 6:03 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 2

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

Feng, Y.P.; Lai, B.; McNulty, I.; Dejus, R.J.; Randall, K.J. & Yun, W. Beam transport radiation shielding for branch lines 2-ID-B and 2-ID-C, report, August 1, 1995; Illinois. (digital.library.unt.edu/ark:/67531/metadc620416/: accessed October 19, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.