1. ECN629801
ENGINEERING CHANGE NOTICE - - - -----------
Pge~ 1 a1 z N2. ECN Category
(mark one)
Supplemental
Direct Revision
Change ECN
Temporary
Standby
Supersedure
Cancel/VoidDE
11
El
E1
QI
E1
Q3. Originator's Name, Organization, MSIN,
and Telephone No.
H. ROBERT WOODWORTH,
19330 L1-02, 373-44924. US Required?
[] Yes [X] No10-23-98
6. Project Title/No./Work Order No. 7. Bldg./Sys./Fac. No. 8. Approval Designator
324 FACILITY B-CELL CLEAN-OUT, 324 Q
r o0 2.9 j418/A3 As j, _9. Document Numbers Changed by this EOW
(includes sheet no. and rev.)
HNF-2286, REV 510. Related ECM No(s).
N/A11. Related PO No.
N/A12a. Modification Work 12b. Work Package 12c. Modification Work Complete 12d. Restored to Original Condi-
No. tion (Temp. or Standby ECN only)
[] Yes (fill out Bk. N/A N/A N/A
12b)
[X] No (NA Blks. 12b, Design Authority/Cog. Engineer Design Authority/Cog. Engineer
12c, 12d) Signature & Date Signature & Date
13a. Description of Change 13b. Design Baseline Document? [] Yes [X] No
DIRECT REVISION OF SUPPORTING DOCUMENT HNF-2286.
REPLACE DOCUMENT HNF-2286, REV. 5, PAGES 1 THROUGH 17, WITH ATTACHED DOCUMENT
HNF-2286, REV. 6, PAGES 1 THROUGH 20.
CHANGES INCLUDE:
1). AD TABLE 5B, PAGES 17-19, "TABLE 5B - SIZE REDUCE THE 2A RACK".
2). REMOVE REFERENCE TO TABLE 5, ON LIST OF "TABLES TO BE ADDED BY DOCUMENT
REVISION", PAGE 20.
3). UPDATE "REMOVE THE 2A RACK" AND "SIZE REDUCE THE 2A RACK" SUMMARIES AS SHOWN ON
PAGE 2.
14a. Justification (mark one)
Criteria Change [X] Design Improvement [] Environmental [] Facility Deactivation []
As-Found [] Facilitate Const [] Const. Error/Omission [] Design Error/Omission []
14b. Justification Details
AS THE QUALITY PROCESS PLAN FOR THE 324 BUILDING ACTIVITIES DEVELOP,
ADDITIONAL TABLES WILL BE ADDED TO HNF-2286.
15. Distribution (include name, MSIN, and no. of copies)
RIDDELLE, JG L1-02 s 9
NORTON, SH L1-02
SANDOZ, DH L5-65 I A .
LENKERSDORFER, KA L1-05 -7
WOODWORTH, HR L1-02
CENTRAL FILES B1-07 -
RL Reading Room H2-53
A-7900-013-2 (05/96) GEF095A-7900-013-1
5. Date
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
RIDDELLE, J.G. 324 Facility B-cell quality process plan, report, November 24, 1998; United States. (https://digital.library.unt.edu/ark:/67531/metadc620408/m1/1/: accessed April 10, 2024), University of North Texas Libraries, UNT Digital Library, https://digital.library.unt.edu; crediting UNT Libraries Government Documents Department.