Department of Energy: Better Information Needed to Determine If Nonmajor Projects Meet Performance Targets

PDF Version Also Available for Download.

Description

A letter report issued by the Government Accountability Office with an abstract that begins "Of the 71 nonmajor projects that the Department of Energy's (DOE) Office of Environmental Management (EM) and National Nuclear Security Administration (NNSA) completed or had under way from fiscal years 2008 to 2012, 21 met or are expected to meet their performance targets for scope, cost, and completion date. These projects included a $22 million EM project to expand an existing waste disposal facility at the Oak Ridge Reservation in Tennessee and a $199 million NNSA project to equip a radiological laboratory and office building at ... continued below

Creation Information

United States. Government Accountability Office. December 19, 2012.

Context

This report is part of the collection entitled: Government Accountability Office Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

A letter report issued by the Government Accountability Office with an abstract that begins "Of the 71 nonmajor projects that the Department of Energy's (DOE) Office of Environmental Management (EM) and National Nuclear Security Administration (NNSA) completed or had under way from fiscal years 2008 to 2012, 21 met or are expected to meet their performance targets for scope, cost, and completion date. These projects included a $22 million EM project to expand an existing waste disposal facility at the Oak Ridge Reservation in Tennessee and a $199 million NNSA project to equip a radiological laboratory and office building at the Los Alamos National Laboratory in New Mexico. Another 23 projects did not meet or were not expected to meet one or more of their three performance targets for scope, cost, and completion date. Among these, 13 projects met or are expected to meet two targets, including a $548 million NNSA project to shut down a nuclear reactor in Russia for nonproliferation purposes; 8 projects met or are expected to meet one target; 1 project did not meet any of its targets; and 1 project was cancelled. Of the remaining 27 projects, many had insufficiently documented performance targets for scope, cost, or completion date, which prevented GAO from determining whether they met their performance targets. EM and NNSA often did not follow DOE requirements for documenting these performance targets, making it more difficult for GAO and DOE to independently assess project performance."

Subjects

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

Collections

This report is part of the following collection of related materials.

Government Accountability Office Reports

The U.S. Government Accountability Office (GAO) is an independent, nonpartisan agency that works for the U.S. Congress investigating how the federal government spends taxpayers' money. Its goal is to increase accountability and improve the performance of the federal government. The Government Accountability Office Reports Collection consists of over 13,000 documents on a variety of topics ranging from fiscal issues to international affairs.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • December 19, 2012

Added to The UNT Digital Library

  • June 12, 2014, 7:50 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 4

Where

Geographical information about where this report originated or about its content.

Place Name

Publication Place

Map Information

  • map marker Automatically generated Place Name coordinates.
  • map marker Automatically generated Publication Place coordinates.
  • Repositioning map may be required for optimal printing.

Mapped Locations

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

United States. Government Accountability Office. Department of Energy: Better Information Needed to Determine If Nonmajor Projects Meet Performance Targets, report, December 19, 2012; Washington D.C.. (digital.library.unt.edu/ark:/67531/metadc301149/: accessed December 18, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.