A letter report issued by the Government Accountability Office with an abstract that begins "The Department of Veterans Affairs (VA) operates one of the largest health care systems in the country. As of August 2009, VA's Veterans Health Administration (VHA) had 32 major ongoing construction projects with an estimated total cost of about $6.1 billion and average cost per project of about $191 million. Some of these projects were initiated as part of VA's Capital Asset Realignment for Enhanced Services (CARES) process, which was a comprehensive assessment of VHA's capital asset requirements. In response to a congressional request, GAO (1) ... continued below

Creation Information

United States. Government Accountability Office. December 14, 2009.

Context

This report is part of the collection entitled: Government Accountability Office Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Description

A letter report issued by the Government Accountability Office with an abstract that begins "The Department of Veterans Affairs (VA) operates one of the largest health care systems in the country. As of August 2009, VA's Veterans Health Administration (VHA) had 32 major ongoing construction projects with an estimated total cost of about $6.1 billion and average cost per project of about $191 million. Some of these projects were initiated as part of VA's Capital Asset Realignment for Enhanced Services (CARES) process, which was a comprehensive assessment of VHA's capital asset requirements. In response to a congressional request, GAO (1) described how costs and schedules of current VHA major construction projects have changed, (2) determined the reasons for changes in costs and schedules, and (3) described the actions VA has taken to address cost increases and schedule delays. To do its work, GAO reviewed construction documents, visited three construction sites, and interviewed VA officials."

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

Collections

This report is part of the following collection of related materials.

Government Accountability Office Reports

The U.S. Government Accountability Office (GAO) is an independent, nonpartisan agency that works for the U.S. Congress investigating how the federal government spends taxpayers' money. Its goal is to increase accountability and improve the performance of the federal government. The Government Accountability Office Reports Collection consists of over 13,000 documents on a variety of topics ranging from fiscal issues to international affairs.

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • December 14, 2009

Added to The UNT Digital Library

  • June 12, 2014, 7:50 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 4

Where

Geographical information about where this report originated or about its content.

Place Name

Publication Place

Map Information

  • map marker Automatically generated Place Name coordinates.
  • map marker Automatically generated Publication Place coordinates.
  • Repositioning map may be required for optimal printing.

Mapped Locations

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

Citations, Rights, Re-Use

United States. Government Accountability Office. VA Construction: VA Is Working to Improve Initial Project Cost Estimates, but Should Analyze Cost and Schedule Risks, report, December 14, 2009; Washington D.C.. (digital.library.unt.edu/ark:/67531/metadc295729/: accessed October 22, 2017), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.