Production of Pu from separations plants and output of unfabricated Pu exceeded commitments. Purex plant set a new record high for U processed. Production and shipments of UO{sub 3} met schedules. Purex solvent extraction battery performed below normal, probably because of poor solvent quality. NaOH addition to Redox coating removal waste is being reduced. A 3fold improvement in Recuplex product Al impurity was achieved by means of a specific gravity difference > 0.15 between dilute aqueous feed and extractant. Sintered, high-silica crucibles are being tested in RMA production line in Finished Products Operation. Scope design of a fission product shipping …
continued below
Publisher Info:
General Electric Co., Richland, WA (United States). Hanford Atomic Products Operation
Place of Publication:
Richland, Washington
Provided By
UNT Libraries Government Documents Department
Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.
Descriptive information to help identify this report.
Follow the links below to find similar items on the Digital Library.
Description
Production of Pu from separations plants and output of unfabricated Pu exceeded commitments. Purex plant set a new record high for U processed. Production and shipments of UO{sub 3} met schedules. Purex solvent extraction battery performed below normal, probably because of poor solvent quality. NaOH addition to Redox coating removal waste is being reduced. A 3fold improvement in Recuplex product Al impurity was achieved by means of a specific gravity difference > 0.15 between dilute aqueous feed and extractant. Sintered, high-silica crucibles are being tested in RMA production line in Finished Products Operation. Scope design of a fission product shipping cask was completed; powder temperature should be below 440 F for 1 MCi cerium-144 + impurities. Feasibility of using one outside Purex canyon entrance (stairwell opening) for relief damper opening was tested and found to be insufficient. A drawing of the 6-inch continuous centrifuge being evaluated as a vacuum drum filter on RMA button line was reviewed. Casks were designed for the NPR project. (DLC)
This report is part of the following collection of related materials.
Office of Scientific & Technical Information Technical Reports
Reports, articles and other documents harvested from the Office of Scientific and Technical Information.
Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.