SM-1 Reactor Core Inspection at 2/3 Core Life : March 7, 1959 to May 17, 1959

One of 93 reports in the series: AEC Research and Development Report available on this site.

PDF Version Also Available for Download.

Description

Abstract: This technical report is concerned with the program and results of the SM-1 reactor vessel head removal and core inspection at Fort Belvoir, Virginia from the period March 7, 1969 to May 17, 1959. It covers the operating procedures in detail and records the conditions found and problems encountered in order to make a record for reference in future work of this nature. The major objective of the program, to obtain irradiation data on the SM-1 type core, has been met. The boron control rod elements were found unsatisfactory for full core life, and europium oxide elements were placed … continued below

Physical Description

xv, 163 pages ; illustrations.

Creation Information

Obrist, C. H.; Byrne, B. J.; Connolly, T. F.; Foley, D. D.; Lichtenberger, R. V.; Mackay, S. D. et al. January 13, 1960.

Context

This report is part of the collection entitled: Technical Report Archive and Image Library and was provided by the UNT Libraries Government Documents Department to the UNT Digital Library, a digital repository hosted by the UNT Libraries. It has been viewed 13 times. More information about this report can be viewed below.

Who

People and organizations associated with either the creation of this report or its content.

Publisher

Audiences

We've identified this report as a primary source within our collections. Researchers, educators, and students may find this report useful in their work.

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this report. Follow the links below to find similar items on the Digital Library.

Titles

Description

Abstract: This technical report is concerned with the program and results of the SM-1 reactor vessel head removal and core inspection at Fort Belvoir, Virginia from the period March 7, 1969 to May 17, 1959. It covers the operating procedures in detail and records the conditions found and problems encountered in order to make a record for reference in future work of this nature. The major objective of the program, to obtain irradiation data on the SM-1 type core, has been met. The boron control rod elements were found unsatisfactory for full core life, and europium oxide elements were placed in the core for future irradiation stability data. A major problem was experienced with the cracked pressure vessel head studs. The methods developed for the removal of the broken studs are presented. The complete metallurgical study of the stud failure from stress corrosion is included as Appendix B.

Physical Description

xv, 163 pages ; illustrations.

Notes

Digitized from microopaque cards.

Contract no. AT(30-3)-326 with U.S. Atomic Energy Commission, New York Operations Office.

Includes bibliographic references (page 163).

Language

Item Type

Identifier

Unique identifying numbers for this report in the Digital Library or other systems.

  • Report No.: APAE-55
  • Grant Number: AT(30-3)-326
  • SuDoc Number: Y 3.AT 7:22/APAE-55
  • Accession or Local Control No: metadc1201955
  • Archival Resource Key: ark:/67531/metadc1201955

Collections

This report is part of the following collections of related materials.

Technical Report Archive and Image Library

The Technical Report Archive & Image Library (TRAIL) identifies, acquires, catalogs, digitizes and provides unrestricted access to U.S. government agency technical reports. The mission of TRAIL is to ensure preservation, discoverability, and persistent open access to government technical publications regardless of form or format.

TRAIL Microcard Collection

Imaged from microcard, these technical reports describe research performed for U.S. government agencies from the 1930s to the 1960s. The reports were provided by the Technical Report Archive and Image Library (TRAIL).

What responsibilities do I have when using this report?

When

Dates and time periods associated with this report.

Creation Date

  • January 13, 1960

Added to The UNT Digital Library

  • Aug. 15, 2019, 10:26 p.m.

Description Last Updated

  • April 23, 2020, 6:03 p.m.

Usage Statistics

When was this report last used?

Yesterday: 0
Past 30 days: 0
Total Uses: 13

Interact With This Report

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

International Image Interoperability Framework

IIF Logo

We support the IIIF Presentation API

Obrist, C. H.; Byrne, B. J.; Connolly, T. F.; Foley, D. D.; Lichtenberger, R. V.; Mackay, S. D. et al. SM-1 Reactor Core Inspection at 2/3 Core Life : March 7, 1959 to May 17, 1959, report, January 13, 1960; Schenectady, New York.. (https://digital.library.unt.edu/ark:/67531/metadc1201955/: accessed November 18, 2025), University of North Texas Libraries, UNT Digital Library, https://digital.library.unt.edu; crediting UNT Libraries Government Documents Department.

Back to Top of Screen