WSRC Reactor Tank Inspection Program (RTIP) status report

PDF Version Also Available for Download.

Description

Westinghouse Savannah River Company (WSRC) recently completed the initial phase of nondestructive inspections of the Savannah River Site's (SRS) reactor tanks. This program required almost three years to be conceptualized, fabricated, and tested. An additional 20 months were required to complete the NDE inspection of the P, K and L reactor tanks. The overall cost of the program to date is approximately $25 MM. This status report will address: (1) A brief review of the RTIP program and the constraints which had to be overcome (2) A summary of the examination results of the P,K, and L Reactor tanks. (3) ... continued below

Physical Description

Pages: (20 p)

Creation Information

Loibl, M.W. January 1, 1992.

Context

This article is part of the collection entitled: Office of Scientific & Technical Information Technical Reports and was provided by UNT Libraries Government Documents Department to Digital Library, a digital repository hosted by the UNT Libraries. It has been viewed 19 times . More information about this article can be viewed below.

Who

People and organizations associated with either the creation of this article or its content.

Author

Sponsor

Publisher

Provided By

UNT Libraries Government Documents Department

Serving as both a federal and a state depository library, the UNT Libraries Government Documents Department maintains millions of items in a variety of formats. The department is a member of the FDLP Content Partnerships Program and an Affiliated Archive of the National Archives.

Contact Us

What

Descriptive information to help identify this article. Follow the links below to find similar items on the Digital Library.

Description

Westinghouse Savannah River Company (WSRC) recently completed the initial phase of nondestructive inspections of the Savannah River Site's (SRS) reactor tanks. This program required almost three years to be conceptualized, fabricated, and tested. An additional 20 months were required to complete the NDE inspection of the P, K and L reactor tanks. The overall cost of the program to date is approximately $25 MM. This status report will address: (1) A brief review of the RTIP program and the constraints which had to be overcome (2) A summary of the examination results of the P,K, and L Reactor tanks. (3) A projection of the future enhancements and capabilities presently in development.

Physical Description

Pages: (20 p)

Notes

OSTI; NTIS; GPO Dep.

Source

  • 33. weapons agencies nondestructive testing organization (WANTO) meeting, Livermore, CA (United States), 10-12 Mar 1992

Language

Item Type

Identifier

Unique identifying numbers for this article in the Digital Library or other systems.

  • Other: DE92013093
  • Report No.: WSRC-MS-92-105
  • Report No.: CONF-9203120--5
  • Grant Number: AC09-89SR18035
  • DOI: 10.2172/10144832 | External Link
  • Office of Scientific & Technical Information Report Number: 5333724
  • Archival Resource Key: ark:/67531/metadc1069953

Collections

This article is part of the following collection of related materials.

Office of Scientific & Technical Information Technical Reports

Reports, articles and other documents harvested from the Office of Scientific and Technical Information.

Office of Scientific and Technical Information (OSTI) is the Department of Energy (DOE) office that collects, preserves, and disseminates DOE-sponsored research and development (R&D) results that are the outcomes of R&D projects or other funded activities at DOE labs and facilities nationwide and grantees at universities and other institutions.

What responsibilities do I have when using this article?

When

Dates and time periods associated with this article.

Creation Date

  • January 1, 1992

Added to The UNT Digital Library

  • Feb. 4, 2018, 10:51 a.m.

Description Last Updated

  • May 15, 2018, 4:23 p.m.

Usage Statistics

When was this article last used?

Yesterday: 0
Past 30 days: 1
Total Uses: 19

Interact With This Article

Here are some suggestions for what to do next.

Start Reading

PDF Version Also Available for Download.

International Image Interoperability Framework

IIF Logo

We support the IIIF Presentation API

Loibl, M.W. WSRC Reactor Tank Inspection Program (RTIP) status report, article, January 1, 1992; Aiken, South Carolina. (digital.library.unt.edu/ark:/67531/metadc1069953/: accessed December 15, 2018), University of North Texas Libraries, Digital Library, digital.library.unt.edu; crediting UNT Libraries Government Documents Department.