- Hallam Nuclear Power Facility, Reactor Operations Analysis Program: Semiannual Progress Report Number 2, March-August 1963
- From summary: The full 140 element loading of the core was completed on October 10, 1962. At this point, critical operation was begun for operator training and post-critical testing purposes.
- Hallam Nuclear Power Facility, Reactor Operations Analysis Program: Semiannual Progress Report Number 3, September 1963-February 1964
- From introduction: This report provides industry, plant operators, and the scientific community with information covering the results of the performance analysis.