Corrosion Product Activity Distribution Across the Chemical Process System in the Consolidated Edison Thorium Reactor Plant

Description: A study has been performed to determine the corrosion product and water impurity activities in the CETR Chemical Process System. A simplified mathematical model is used to represent the physical situation; however, the magnitude of the activities, taken at the end of the core life to represent the most conservative case, is considered sufficiently accurate for engineering calculations.
Date: August 1960
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Development and Testing of Low Cost Fuel Elements for Power Reactor Service

Description: The development of swaging and vibratory compaction process for fabrication of clad UO2 fuel rods is described. The cost is less than 50% of that for an equivalent core fabricated from pellets. The irradiation testing of vibratory filled and swaged UO2 rods is reported for burn-ups from 2,000 to 12,000 Mwd/t UO2; the results indicate that the rods are capable of excellent performance power reactors.
Date: June 2, 1961
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Irradiation Performance of Thoria-Urania Fuel Materials: Quarterly Technical Report, Number 2, October - December 1964

Description: From introduction: "Complete exploitation of the advantages of thorium as a fertile material in thermal and particular resonant spectrum reactors has been inhibited by the lack of quantitative physical property data for thoria and thoria-urania fuels."
Date: October 1964
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Annual Technical Report: 1958

Description: Annual report of the Liquid Metal Fuel Reactor Experiment describing progress during calendar year 1958 and as well as an evaluation of progress and plans for future work.
Date: March 25, 1959
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: April 1957

Description: A monthly report summarizing work perform by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. In this monthly report information on the reactor design No. 10 had been selected as the LMFRE preliminary reference design, various shielding designs have bee studied, various calculations on multiregion code and reactivity have been continued, and other related to the LMFRE
Date: April 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: August, 1957

Description: A monthly report summarizing work performed by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. In this monthly report the R&D budget was reviewed, two-dimensional calculations were performed, analysis work was started on control rods and their housing, as well as continued work on the development of the LMFRE reactor.
Date: August 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: December 1956

Description: A monthly report summarizing work perform by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. Preliminary design studies for nuclear reactor development and its components were reported.
Date: December 1956
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: February 1957

Description: A monthly report summarizing work perform by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. Included in this report was a study made regarding the possible use of beryllium as a core moderating material, calculations made regarding temperature distribution for various channel sizes and power levels, design parameters for initial operation of the LMFRE, and other work in the design and operation of the reactor.
Date: February 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: January 1957

Description: A monthly report summarizing work perform by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. Initial contacts were made at National Reactor Testing Station and Hanford Works, design conditions for the proposed reactor vessels were reviewed, estimates of heating rates caused by radiation and the pluggage of fuel passages were computed, and design parameters for the LMFRE were established.
Date: January 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: July, 1957

Description: A monthly report summarizing work perform by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. In this months report includes specifications a utility loop, further calculations for fuel rods, drawings were reviewed and specifications for the core reactor were reviewed.
Date: July 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: June 1957

Description: A monthly report summarizing work perform by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. This month's report includes information on various factors entering into the estimate of reference design core which has been analyzed for sources of error, further design and testing procedures on the nuclear core, and other work focused on construction and design elements.
Date: June 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: March 1957

Description: A monthly report summarizing work perform by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. In this monthly report work was reported on a completed study of the change in critical concentration and critical diameter with small changes in the physical and nuclear parameters of the reference design, reactor design #8 which incorporates an integral graphite core and core tank has been completed and distributed, and other work required for the design and construction of a LMFRE.
Date: March 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: May 1957

Description: A monthly report summarizing work perform by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. This month's report includes the Research and Development program was completed, a study of shielding requirements indicated the necessity for test data, more information on studies regarding reactor startup, and other developments related to develop the LMFRE.
Date: May 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment Monthly Progress Statement: September, 1957

Description: A monthly report summarizing work performed by Babcock & Wilcox personnel for the U.S. Atomic Energy Commission. In this month's report comparison of second two-dimensional calculation with the equivalent one-dimensional calculations was performed, reference design core modifications were completed, along with continued work on the design of the core and containment vessel for a LMRFE.
Date: September 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment: Quarterly Technical Report No. 1, BAW-1001, July 1, 1956 to November 15, 1956

Description: This is the first quarterly report which summarizes the project work on the Liquid Metal Fuel Reactor Experiment. As the initial contract was not signed until November, 1956, progress within this reporting period has been limited to establishing objectives, determining what research and development will be required, and selecting preliminary design parameters.
Date: 1956-07/1956-11
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor Experiment: Reference Design Report

Description: Report concerning preliminary designs of the Liquid Metal Fuel Reactor Experiment (LMFRE) facility. This includes descriptions of the reactor, degasser, and steam system, materials to be used, plant arrangement, building siting, and safety considerations.
Date: August 1957
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department
open access

Liquid Metal Fuel Reactor, Technical Feasibility Report

Description: Report concerning the technical feasibility of a full-scale Liquid Metal Fuel Reactor, including metallurgical, mechanical, and engineering evaluations.
Date: June 30, 1955
Creator: Babcock & Wilcox Company
Partner: UNT Libraries Government Documents Department