DCN 11538
Flaws in the Red River Recommendation
* The Industrial Joint Cross Service Group (IJCSG)
reached its recommendation to close Red River Army
Depot using a flawed methodology.
- DoD handbook uses a workload of 85% capacity based on 1
shift, 8 hours/day or 40 hours per week for capacity analysis.
- No excess capacity exists beyond necessary surge ratio.
- Industrial JCSG incorrectly used 60 hours per week (1.5 shifts),
making it appear feasible to close Red River and leading to the
flawed Red River recommendation.
* This flaw required the creation of 2.6 million direct labor
hours in new capacity to support the Red River closure.
- Recommendation requires creation of 2.2 M DLH in capacity at
Anniston and 0.4 M DLH in capacity at Letterkenny.
- Recommendation requires over $194 M in one time costs and
over $40 M in military construction to recreate capacity that
exists at Red River today.
Upcoming Pages
Here’s what’s next.
Search Inside
This text can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Text.
A 20 - Red River Army Depot, TX, Community Presentation, text, November 8, 2005; (https://digital.library.unt.edu/ark:/67531/metadc24485/m1/14/: accessed April 24, 2024), University of North Texas Libraries, UNT Digital Library, https://digital.library.unt.edu; crediting UNT Libraries Government Documents Department.